Key Facts

Permit required
before building any 1- or 2-family dwelling
Issued by
Village; copy filed with Village Clerk
Expiration
automatic after 2 years if not completed
Fee
set by the Village Board
Enforced by
certified Building Inspector
Other structures
separate permit under § 234-10
General penalty
§ 1-2, $10-$500 forfeiture

Summary

Rothschild requires a state uniform building permit before building any one- or two-family dwelling, issued through the Village and filed with the Village Clerk, under Code § 234-2. The permit automatically expires if the project is not finished within two years, and a separate Article II permit under § 234-10 covers other structures and flammable-liquid or gas storage.

No person shall build or cause to be built any one- or two-family dwelling without first obtaining a state uniform building permit for such dwelling. Such building permit shall be furnished by the Village of Rothschild. A copy of such permit issued shall be filed with the Village Clerk. A permit shall be automatically revoked if the project set forth on the permit is not completed within two years from the date of issuance of the permit.

Full Breakdown

Chapter 234's Article I adopts the Wisconsin Uniform Dwelling Code, incorporating Wis. Adm. Code Chs. SPS 320 through 325, and directs a Building Inspector certified by the state Department of Safety and Professional Services to administer and enforce it. Section 234-2 requires a state uniform building permit before building any one- or two-family dwelling; the Village issues the permit, a copy goes to the Village Clerk, and the permit automatically expires if the project is not finished within two years of issuance. Section 234-3 leaves the fee itself to the Village Board rather than fixing a dollar figure in the code.

Article II applies a parallel scheme to everything else: § 234-6 subjects new commercial buildings, alterations, additions, repairs and maintenance other than one- and two-family dwellings to the Wisconsin Commercial Building Code, Wis. Adm. Code Chs. SPS 361 through 366, while § 234-10 requires its own uniform building permit, filed the same way, for building, altering, repairing or maintaining a structure, or for storing flammable liquid or gas, with the same two-year automatic revocation. Section 234-7 layers additional state code requirements onto storage of flammable and combustible liquids, LP and natural gas, and anhydrous ammonia, and § 234-8 requires drain tile on all below-grade construction unless the soil is sandy gravel with groundwater and bedrock more than seven feet down.

Violations & Fines

Violating Chapter 234, including building without the required permit, is enforced under § 234-4 by the Village Board withholding building permits from the project, plus the Village's general penalty in § 1-2: a forfeiture of $10 to $100 for a first offense and $50 to $500 for a repeat offense within a year, plus prosecution costs and up to six months in jail if unpaid.

Frequently Asked Questions

Do I need a permit to build a house in Rothschild?
Yes. Village Code § 234-2 requires a state uniform building permit before building any one- or two-family dwelling. The Village issues the permit, a copy is filed with the Village Clerk, and the permit automatically expires if the project is not completed within two years.
Who enforces Rothschild's building permit requirements?
The Building Inspector, certified by the Wisconsin Department of Safety and Professional Services, administers and enforces the Uniform Dwelling Code under § 234-1B. The Village Board also enforces Chapter 234 generally by withholding building permits from noncompliant projects, per § 234-4.
How much does a Rothschild building permit cost?
Village Code § 234-3 does not set a fixed dollar figure; it leaves the building permit fee to be determined by the Village Board, so applicants should check the Village's current fee schedule before applying.
Does the dwelling permit also cover commercial buildings?
No. Section 234-2 covers only one- and two-family dwellings. New commercial buildings, alterations and additions are subject to the Wisconsin Commercial Building Code, Wis. Adm. Code Chs. SPS 361 through 366, under § 234-6, and structures storing flammable liquids or gas need a separate permit under § 234-10.

Sources & Official References

Other rules in Rothschild

All Rothschild rules

Compare Rothschild to another location·View the Wisconsin building safety overview

Get notified when Building Permits in Rothschild, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Marathon County handle building permits.

Wausau, WI
Some Restrictions