Key Facts

Permit trigger
Before footing/foundation excavation or construction, alteration, remodel
Who can apply
Owner, contractor, or party performing the work
Fee schedule
Set under Wausau Municipal Code § 3.40.010(a)
Plan review
Required before permit issues, per § 15.20.020
Commercial plan review
City is Delegated Agent Municipality, SPS 361.60/382
Occupancy hold
Withheld until sewer/water connections inspected, § 15.20.040

Summary

The City of Wausau requires a building permit signed by the Building Inspector before footing and foundation excavation or before construction, alteration, remodeling, or moving of any building or structure begins within city limits, per Wausau Municipal Code Section 15.20.010. The owner, contractor, or whoever performs the work can obtain the permit, and any of them can be prosecuted for skipping it. Permit fees are set under Section 3.40.010(a), payable to the City Treasurer.

A building permit signed by the Building Inspector shall be obtained before footing and foundation excavation or the commencement of construction, alteration or remodeling or moving of any building or structure within the City. The building permit may be obtained by the owner or contractor or by the party by whom the work is to be performed; any or all of the foregoing may be prosecuted for failure to obtain the permit. The fees payable to the City treasurer for building permits shall be as set forth in section 3.40.010(a).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 12 Update 2).

Full Breakdown

Before any footing or foundation excavation, or before construction, alteration, remodeling, or moving of a building or structure, Wausau Municipal Code Section 15.20.010 requires a building permit signed by the City's Building Inspector. The permit can be secured by the property owner, the contractor, or the party actually performing the work, and the code allows prosecution of any of them for proceeding without one. Permit fees are billed at the rate the Common Council sets in Section 3.40.010(a) and are payable to the City Treasurer.

Section 15.20.020 adds that no building permit issues for a new building or structure until the Building Inspector approves plans and specifications, including a plot plan showing the building's location relative to property lines and enough detail to show the exact construction to be performed. For commercial work, Section 15.20.025 has Wausau operating as a Delegated Agent Municipality under Wisconsin Administrative Code SPS 361.60 and SPS 382, so the City's own certified commercial building inspectors handle plan examination and inspection for new commercial buildings, additions, and alterations to fire alarm, sprinkler, plumbing, or HVAC systems, rather than routing those plans to the state.

Section 15.20.040 places further conditions on permits (though not on a private garage or accessory building): the abutting street grade must already be approved by the Common Council, or be at a grade the City Engineering Department finds acceptable, and water and sewer mains must already reach the abutting street or be programmed for installation the following year. Even after those conditions are met, the City withholds the occupancy permit until the building is actually connected to the sewer and water main and the City has inspected and approved those connections.

Violations & Fines

Proceeding with excavation, construction, alteration, remodeling, or a building move without a Section 15.20.010 permit exposes the owner, the contractor, and whoever performed the work to prosecution, since the code names all three as potentially liable. Building without an approved plan set under Section 15.20.020, or before the street-grade and utility conditions in Section 15.20.040 are met, blocks permit issuance outright, and the City will not issue an occupancy permit until sewer and water connections are inspected and approved.

Frequently Asked Questions

Do I need a permit to build a garage in Wausau?
Yes. Section 15.20.010 requires a building permit before construction of any building or structure, which includes a private garage. Garages and accessory buildings are only exempt from the separate street-grade and utility-connection conditions in Section 15.20.040, not from the underlying permit requirement itself.
Who is responsible for obtaining a Wausau building permit?
Section 15.20.010 lets the property owner, the contractor, or the party actually performing the work obtain the permit, and it allows the City to prosecute any of them if the work proceeds without one.
When can Wausau withhold an occupancy permit?
Under Section 15.20.040, the City will not issue an occupancy permit until the building has been connected to the City sewer and water mains and those connections have been inspected and approved.
Does Wausau review commercial building plans itself?
Yes. Section 15.20.025 designates Wausau a Delegated Agent Municipality under Wisconsin Administrative Code SPS 361.60 and SPS 382, so the City's own certified commercial building inspectors handle plan examination for new commercial buildings and system additions rather than the State doing it.

Sources & Official References

Other rules in Wausau

All Wausau rules

Compare Wausau to another location·View the Wisconsin building safety overview

Get notified when Building Permits in Wausau, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.