Santa Ana, CA Building Safety: Building Permits (2026)
Key Facts
- Permit trigger
- Any construction, alteration, or occupancy change
- Minor exemption
- Sidewalks/decks 30 in. or less above grade
- Application lapse
- Abandoned after 180 days unless issued
- Extension
- One extension, up to 180 more days
- Certificate of occupancy lapse
- Abandoned after 12 months
- Renewal cost
- New plan review fee to resubmit
Summary
No building or structure in Santa Ana may be erected, altered, repaired, moved, or have its occupancy changed without a separate permit for each structure from the building official. Sec. 8-94 sets that baseline, and Sec. 8-96 voids any application left unresolved for 180 days.
105.1 Permits required. No building or structure regulated by this code shall be erected, constructed, enlarged, altered, repaired, moved, improved, or its occupancy changed, removed, converted, demolished or maintained unless a separate permit for each building or structure has first been obtained from the building official... Sec. 105.3.2. Time limitation of application. An application for a permit for any proposed work shall be deemed to have been abandoned 180 days after the date of filing, unless the permit has been issued; except that the Building Official may extend the time for action by the applicant for a period not exceeding one hundred and eighty (180) days upon request by the applicant showing that circumstances beyond the control of the applicant have prevented action from being taken. No application shall be extended more than once.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 32).
Full Breakdown
Sec. 2 so that only sidewalks, driveways, and decks 30 inches or less above grade, not over a basement, and not part of an accessible route are exempt from needing a permit at all. Sec. 8-96 then puts a clock on the process: an application is deemed abandoned 180 days after filing unless a permit has issued, though the building official can grant a single extension of up to 180 more days if the applicant shows delay was beyond their control, no application gets extended twice, and reviving an abandoned application means resubmitting plans and paying a new plan review fee.
A related certificate-of-occupancy application is deemed abandoned 12 months after filing on the same terms. Sec. 8-95 folds inspection into this permit track: no building may be occupied and no occupancy classification may change until the building official issues a certificate of occupancy, and any alteration that changes floor area or means of egress needs its own certificate of occupancy first. A business operating inconsistently with its certificate of occupancy is treated as a Code violation, and utilities can be disconnected until a follow-up inspection confirms compliance.
Violations & Fines
Sec. 8-95(4) makes occupying a building or operating a business without a valid certificate of occupancy a Code violation that can result in disconnection of any or all utilities; reconnection requires a building official inspection confirming compliance. Letting a permit application sit unresolved past the 180-day window under Sec. 8-96 forces the applicant to resubmit plans and pay a new plan review fee rather than simply reactivate the old file.
Frequently Asked Questions
Do I need a permit to remodel a building in Santa Ana?
How long does a Santa Ana building permit application stay active?
What happens if my permit application lapses?
Is a small deck exempt from Santa Ana's permit requirement?
Sources & Official References
Other rules in Santa Ana
California rules heatmap·Compare Santa Ana to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.