Southampton Village, NY Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Issuing official
Building Inspector, one permit per building or structure
Exemption
Ordinary repairs that are not structural in nature
Decision deadline
60 days from submission of the application
Permit duration
One year, plus one one-year extension
Engineer review
Commercial buildings and residential work costing over $500,000
Early-start penalty
Permit fees doubled

Summary

In the Village of Southampton, a separate building permit from the Building Inspector is required before anyone erects, enlarges, alters, improves or converts a building or structure, or changes its occupancy. Only ordinary repairs that are not structural are exempt. The Building Inspector approves or disapproves within 60 days, and a permit lasts one year.

No person, firm or corporation shall commence the erection, enlargement, alteration, improvement, conversion or change in the nature of the occupancy of any building or structure, or cause the same to be done, without first obtaining a separate building permit from the Building Inspector for each such building or structure; except that no building permit shall be required for the performance of ordinary repairs which are not structural in nature. ... No permit to construct any commercial building, any residence in which the cost of construction shall exceed $500,000 or be in connection with the construction or renovation of an existing dwelling at a cost exceeding $500,000 and construction of dwellings in an approved subdivision by a developer shall be issued until the application, plans, specifications and elevations for the dwellings, on-site parking and site improvements shall have been reviewed by the Village Engineer, and a schedule of minimum inspections shall be prepared for such project, and the Building Inspector shall be required to make such inspections during the course of the construction.

Full Breakdown

Section A119-1 of the Building Construction Regulations, promulgated by the Building Inspector and approved by the Board of Trustees on April 14, 1978, sets the trigger. No person, firm or corporation can commence the erection, enlargement, alteration, improvement, conversion or change in the nature of the occupancy of any building or structure without first obtaining a separate building permit from the Building Inspector for each building or structure. The one carve-out is ordinary repairs that are not structural in nature.

The application goes to the Building Inspector on his forms. It must give a description of the land, a statement of the use or occupancy of all parts of the land and the proposed building, the valuation of the work, the owner's and applicant's names and addresses, a brief description of the work, and the applicant's consent to entry by the Building Inspector and Building Department employees without a search warrant. The owner or the owner's authorized agent signs it, and if someone other than the owner applies, an owner affidavit must confirm the work is authorized. Duplicate copies of plans and specifications, including a scale plot plan showing distances from lot lines, are required, though the Building Inspector can waive plans for minor alterations.

Larger projects get a second review. Under § A119-1(G), a permit for a commercial building, or for a residence or renovation costing more than $500,000, waits for review by the Village Engineer and a schedule of minimum inspections.

Timing and cost follow. Section A119-3 gives the Building Inspector 60 days from submission to approve or disapprove, and § A119-4 makes a permit effective for one year, with a maximum of one extension for one additional year on proof of substantial construction above the foundations. Under § A119-2, residential new buildings and additions pay 1.25% of estimated construction cost, not less than $250, up to $100,000, then 1.5% between $100,000 and $1,000,000 and 1.65% above $1,000,000. Tennis courts and other playing courts pay a $2,000 flat fee, and any application requiring a public hearing pays a one-time $450 public hearing fee.

Violations & Fines

Starting work early costs double: § A119-2(C) doubles the building permit fees when construction is commenced before the application is filed. The Building Inspector can revoke a permit for a material false statement, a permit issued in error, work not following the approved application or plans, or failure to comply with a stop order (§ A119-5). Section A119-6 lets the Building Inspector direct the owner or the owner's agent to suspend all work done in violation or in an unsafe and dangerous manner.

Frequently Asked Questions

Do I need a building permit for repairs in the Village of Southampton?
Not for ordinary repairs that are not structural in nature, which section A119-1(A) exempts. Everything else on the list needs a permit: erection, enlargement, alteration, improvement, conversion, or a change in the nature of the occupancy of any building or structure. Each building or structure needs its own separate permit from the Building Inspector.
How long does the Building Inspector have to decide?
Section A119-3 gives the Building Inspector 60 days from the date of submission to approve or disapprove the application. On disapproval, the plans and specifications go back to the applicant, and on request the Building Inspector sends the refusal and the reasons in writing. On approval and receipt of the fees, the permit issues.
How long is a building permit valid?
Under § A119-4, a permit authorizes the commencing of work for one year after issuance. If the applicant proves substantial construction above the foundations before the expiration date, the Building Inspector can allow a maximum of one extension for one additional year. The permit must be displayed prominently on the job-site while work is in progress.
What happens if I start before filing the application?
Section A119-2(C) provides that if construction is commenced before the application for a building permit is filed, the fees are doubled in connection with issuing the permit for the work. The Building Inspector can also issue a stop order under § A119-6 when work is not in conformity with the permit or the applicable laws.

Sources & Official References

Other rules in Southampton Village

All Southampton Village rules

New York rules heatmap·Compare Southampton Village to another location·View the New York building safety overview

Get notified when Building Permits in Southampton Village, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Suffolk County handle building permits.

Babylon, NY
Some Restrictions
Huntington, NY
Some Restrictions
Islip, NY
Some Restrictions