Skip to main content
CityRuleLookup

Bradenton, FL Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
National Electrical Code, 2005 Edition
Copy on file
City planning and community development department
Conflicts
More restrictive provision prevails under Sec. 18-102
Supervision
Master electricians registered with the city
Temporary power
Temporary service permit; building permit is a prerequisite
Penalty
Sec. 1-15: fine up to $500.00 or 60 days

Summary

Electrical work in the City of Bradenton, Florida is done under the National Electrical Code, 2005 Edition, as adopted by Sec. 18-101, and under the supervision of master electricians registered with the city. The contractor named on the construction permit answers for the whole system, and temporary construction power needs a temporary service permit plus a building permit.

The work under this article shall be performed only under the supervision of master electricians registered with the city as outlined in section 22-31 et seq. of this Code. ... The electrical contractor named on the original construction permit shall be responsible for the entire electrical system installed in the building and the connection of all equipment installed. Special permission may be granted to a second electrical contractor to connect specific equipment only; a special permit shall be required. ... Temporary power for construction shall be from a temporary pole or from existing service; a temporary service permit is required. A building permit is a prerequisite to the temporary electrical service for construction and/or remodeling power. ... There is hereby adopted for the purpose of establishing rules and regulations for electrical work in the city that code known as the National Electrical Code, 2005 Edition, a current copy of which shall remain on file in the city planning and community development department for public use, inspection and examination, and the same is hereby adopted and incorporated as fully as if set out at length herein.

Full Breakdown

Electrical rules in the City of Bradenton are split between Division 2, Inspections, and Division 3, Standards, of Article III in Chapter 18. Sec. 18-101 adopts the National Electrical Code, 2005 Edition, as fully as if set out at length in the Code, and keeps a current copy in the city planning and community development department for public use, inspection and examination. The history note printed after the section lists Ord. No. 2819, § 1, 2-22-06. Sec. 18-102 settles conflicts: if any part of Article III or another city ordinance conflicts with the adopted National Electrical Code, the more restrictive provision prevails.

Who does the work is regulated as well. Sec. 18-79 requires work under the article to be performed only under the supervision of master electricians registered with the city as outlined in Sec. 22-31 et seq. Sec. 18-80 makes the electrical contractor named on the original construction permit responsible for the entire electrical system installed in the building and the connection of all equipment. A second electrical contractor can connect specific equipment only with special permission, and a special permit is required. Under Sec. 18-83, inspections are requested only by the electrical contractor who performed the work.

Temporary power has its own permit. Sec. 18-84 requires temporary power for construction to come from a temporary pole or from existing service, requires a temporary service permit, and makes a building permit a prerequisite to the temporary electrical service for construction and remodeling power.

Permits can be lost or halted. Sec. 18-77 lets the electrical inspector revoke a permit or approval for any false statement or misrepresentation as to a material fact in the application or plans, and permit fees are not refunded in those cases. Sec. 18-76 requires work to stop on written notice from the inspector, or oral notice in an emergency. A cross reference printed under Sec. 18-101 points to Sec. 18-226 et seq. for swimming pools.

Violations & Fines

Article III violations are punished under Sec. 18-56 as provided in Sec. 1-15, in addition to other penalties: a fine of not more than $500.00 or imprisonment not exceeding 60 days, or both, with each day a separate offense. Sec. 18-78 declares hazardous electrical installations illegal and subject to abatement by rehabilitation or removal, and Sec. 18-77 revokes a permit obtained on false information without refunding fees.

Frequently Asked Questions

What edition of the National Electrical Code does Bradenton use?
Sec. 18-101 adopts the National Electrical Code, 2005 Edition, and prints a fixed year. Compare Sec. 18-126, which adopts the most current Florida Plumbing Code with no year. If Article III or another city ordinance conflicts with the adopted National Electrical Code, Sec. 18-102 says the more restrictive provision prevails.
Do I need a permit for temporary power at a Bradenton construction site?
Yes. Sec. 18-84 says temporary power for construction shall come from a temporary pole or from existing service, that a temporary service permit is required, and that a building permit is a prerequisite to the temporary electrical service. Under Sec. 18-82, temporary poles and underground services are inspected before they are energized.
Who is responsible for the electrical system on a permitted job?
Sec. 18-80 makes the electrical contractor named on the original construction permit responsible for the entire electrical system installed in the building and the connection of all equipment. A second contractor connects specific equipment only with special permission and a special permit. Sec. 18-79 adds that work is supervised by registered master electricians.
Can the City of Bradenton revoke an electrical permit?
Yes, in one stated situation. Sec. 18-77 authorizes the electrical inspector to revoke a permit or approval if there has been any false statement or misrepresentation as to the material fact in the application or plans on which the permit or approval was based. In all such cases permit fees are not refunded.

Sources & Official References

Other rules in Bradenton

All Bradenton rules

Florida rules heatmap·Compare Bradenton to another location·View the Florida building safety overview

Get notified when Electrical Permits in Bradenton, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.