Garland, TX Building Safety: Electrical Permits (2026)
Key Facts
- Adopted code
- 2014 National Electrical Code
- Permit issuer
- City Building Official
- Permit expiry
- 2 years without progress
- Project lapse
- 5 years from first application
- Max fine
- Up to $2,000 per violation
- Appeals
- Unified Building Standards Commission
Summary
Garland has adopted the 2014 National Electrical Code and requires a separate electrical permit before any regulated wiring is installed, altered, repaired, replaced or remodeled. Applications go to the Building Official under Code of Ordinances Article III, and a short list of minor repairs, like reinstalling attachment-plug receptacles or replacing an overcurrent device of the same capacity, is exempt from that requirement.
The National Electrical Code, 2014 edition, is hereby adopted by reference. One (1) copy is to remain on file in the City Secretary’s office. Unless deleted, amended, expanded or otherwise changed herein, all provisions of this Code shall be fully applicable, binding, and of full force and effect. ... Permits required. Except as specified in subsection (C) of this section, no electrical system regulated by this Code shall be installed, altered, repaired, replaced or remodeled unless a separate electrical permit for each building or structure has first been obtained from the Building Official, or without first submitting a subcontractor’s affidavit form for work authorized under a combined building permit.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4862189; v40 updated 2026-05-19).
Full Breakdown
52(A) requires a separate electrical permit for each building or structure before any electrical system regulated by the Code is installed, altered, repaired, replaced or remodeled, unless the work is done under a subcontractor's affidavit filed against a combined building permit. 52(C) lists narrow exemptions: portable cord-connected appliances, temporary decorative lighting, taping joints, removing wiring, low-voltage class II/III signal circuits, and repair or replacement of fixed motors, overcurrent devices, or attachment-plug receptacles of the same rating in the same location. None of these exemptions authorizes work that otherwise violates the Code.
53 requires a written application identifying the work, the property, and the intended use, plus plans and specifications when the Building Official requires them; engineering documents for structural, mechanical, plumbing or electrical systems must be prepared by a Texas-licensed engineer when the Building Official finds it necessary. ' A permit expires two years after issuance if no progress has been made, and the underlying project lapses five years after the first application if it never advances. 56 bars connecting the system to a power source until the Building Official approves it, though temporary testing connections may be authorized.
40, governs the technical wiring standards; a copy is kept on file with the City Secretary, and any local amendments are attached to Chapter 30.
Violations & Fines
Doing electrical work without a permit, or performing work under someone else's permit, is a Code violation under section 30.49, punishable under the citywide general penalty in section 10.05: fines run up to $2,000 for fire-safety-related building violations and up to $500 for other Code violations, with each day of noncompliance a separate offense. The Building Official may also suspend or revoke a permit issued in error; appeals of Building Official decisions go to the Unified Building Standards Commission under section 30.50.
Frequently Asked Questions
Do I need a permit to replace a light switch?
How long does a Garland electrical permit stay valid?
Can I get inspected before the wiring is covered?
Sources & Official References
Other rules in Garland
Texas rules heatmap·Compare Garland to another location·View the Texas building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in Dallas County handle electrical permits.