Richardson, TX Building Safety: Electrical Permits (2026)
Key Facts
- Permit authority
- Building inspection department
- Adopted code
- National Electrical Code, 2020 edition
- Late-start penalty
- Permit fee doubled (Sec. 6-92)
- Cable restriction
- NM/NMC/NMS limited to 1-2 family, multifamily
- Contractor requirement
- City registration + state license
Summary
Richardson requires a city-issued permit or contractor's voucher before any electrical wiring, fixture or equipment is installed, altered or repaired within city limits. All work must conform to the National Electrical Code, 2020 edition, adopted by ordinance and enforced by the building inspection department.
Except as otherwise specifically provided in this article, it shall be unlawful for any person to install or cause to be installed, or to permit any person to install, any electrical wiring, fixtures or equipment within or on any building, structure or premises, publicly or privately owned, or to make any alteration, addition, change or repair within the scope of this article, without first having procured a permit therefor issued by the building inspection department or without filing a contractor's voucher with the building inspection department...If work is commenced prior to issuance of a permit, the fee shall be doubled in addition to any other penalties provided for in this article...The National Electrical Code, 2020 edition, NFPA 70 is hereby adopted and incorporated herein by reference and made a part of this article for all purposes, the same as if copied in full herein.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 35 Update 2).
Full Breakdown
Under Sec. 6-91 of the building code chapter, it is unlawful to install, alter or repair electrical wiring, fixtures or equipment on any building or premises, public or private, without first getting a permit from the building inspection department, or filing a contractor's voucher when the work falls under an existing building permit. Skipping the permit step is not just a paperwork problem: Sec. 6-92 doubles the electrical permit fee if work starts before a permit issues, on top of any other penalty. Electrical fees are folded into the building permit fee where one is required; where it is not, a minimum fee from the Master Fee Schedule applies, and a reinspection fee is charged starting with the third reinspection of uncorrected work.
Sec. 6-93 requires a final inspection on every installation, and any electrical work that will be concealed by permanent building parts must be inspected before it is closed in; an inspector can order concealed work reopened if it was covered without notice. Sec. 6-94 bars connecting power to equipment requiring a permit until the electrical inspector issues a certificate of approval, though a temporary connection may be authorized. Technical compliance runs through Sec. 6-132, which adopts the National Electrical Code, 2020 edition (NFPA 70) by reference for all electrical installations citywide, and restricts NM, NMC and NMS cable types to one- and two-family and multifamily dwellings.
All electrical work must be performed by a contractor registered with the city and licensed by the State of Texas as an electrical contractor (Sec. 6-111), with a qualified master electrician responsible for supervising the work.
Violations & Fines
Working without a permit doubles the electrical permit fee under Sec. 6-92, in addition to other penalties this article allows. Electrical inspectors may order service disconnected where wiring is unsafe, unpermitted, or interferes with fire department operations (Sec. 6-74), and the building inspection department can withhold inspections, vouchers or permits from a registered contractor who fails to correct deficient work within ten days of written notice (Sec. 6-96). Interfering with an inspector's official duties is a separate offense under Sec. 6-76.
Frequently Asked Questions
Do I need a permit for minor electrical repairs in Richardson?
What happens if I start electrical work before getting a permit?
Which electrical code applies in Richardson?
Sources & Official References
Other rules in Richardson
Texas rules heatmap·Compare Richardson to another location·View the Texas building safety overview
See something wrong?