Haverford, PA Building Safety: Electrical Permits (2026)
Key Facts
- Issuing official
- Director of Code Enforcement, Haverford Township
- Adopted standard
- National Electrical Code (§ 73-5)
- Drawings threshold
- Signed drawings for new commercial, public, industrial buildings and apartments unless work costs under $2,500
- Inspection certificate
- Due within 15 days after the installation is completed
- Maximum fine
- $1,000 plus costs; each day after notice is a separate offense
- Appeal window
- 10 days, in writing, to the Examining Board
Summary
In Haverford Township, Delaware County, Pennsylvania, no one may perform electrical work without first getting a permit from the Director of Code Enforcement. The Board of Commissioners adopted the National Electrical Code, and violations carry a fine of up to $1,000 plus costs.
No person shall perform any electrical work in the Township unless he first obtains a permit from the Director of Code Enforcement. An applicant for a permit shall make application on a form supplied by the Township, setting forth the following: A. The nature of the electrical work to be performed. B. The place where the electrical work will be done. C. Plans and specifications for the electrical work to be done. Electrical drawings will be required for all new commercial, public and industrial buildings and apartments and shall be signed by an architect or a professional electrical engineer qualified in the commonwealth to prepare such final drawings, plans and specifications, unless the estimated cost of electrical work is less than $2,500. D. The name and address of the person who will perform the electrical work. E. Any other information which the Director of Code Enforcement deems necessary or desirable.
Full Breakdown
Chapter 73 of the Haverford Township Code makes the permit the starting point for all electrical work. Under § 73-7, the applicant files on a township form that states the nature of the work, the place where it will be done, plans and specifications, and the name and address of the person doing the work. Electrical drawings signed by an architect or a professional electrical engineer are required for all new commercial, public and industrial buildings and apartments, unless the estimated cost of the electrical work is less than $2,500. The Director of Code Enforcement can ask for any other information he deems necessary.
The standard is the National Electrical Code, which the Board of Commissioners adopted in § 73-5. That section also limits materials to those on the Underwriters' Laboratories list of inspected appliances and adds a local requirement: wherever electrical work accompanies a gas or oil burner installation, an emergency shutoff switch with a red plate marked "oil burner" or "gas burner" must be installed at the entrance to the basement or heating room. Section 73-8 exempts replacing light bulbs or fuses, minor repair work, plugging a portable appliance into an installed receptacle, and central police station supervised alarm systems.
Permit fees are set by resolution of the Board of Commissioners (§ 73-9). Inspections are made by the Director of Code Enforcement or an approved inspection agency, and a certificate of inspection and approval must reach the Director not later than 15 days after the installation is complete (§ 73-10). The Director can stop work in process and order removal of work that does not conform. A permit can be revoked if work is unsafe, a condition is violated, or active work does not begin within six months of issuance (§ 73-11). Anyone aggrieved can appeal in writing to the Examining Board within 10 days (§ 73-14).
Violations & Fines
Under § 73-16, performing electrical work contrary to the National Electrical Code or Chapter 73, or ignoring an order of the Director of Code Enforcement, is a summary offense before the District Justice. The fine is up to $1,000 plus costs of prosecution, with up to 90 days in county jail on default of payment. After notice, each further day is a separate offense. Non-conforming work is also declared a public nuisance and can be abated (§ 73-15).
Frequently Asked Questions
Who issues electrical permits in Haverford Township?
Do I need an architect or engineer to sign my electrical drawings?
What happens after the electrical work is finished?
How do I appeal a decision of the Director of Code Enforcement?
Sources & Official References
Other rules in Haverford
Compare Haverford to another location·View the Pennsylvania building safety overview