Key Facts

Base fixture fee
$75 for 1 to 50 receptacles, fixtures and switches
Additional items
$15 per increment of 25 items
Service up to 200 amps
$75 per piece of equipment
Temporary service/pole
$90 with GF receptacle
Minimum fee
$85 for R-5 and R-3; $150 all other use groups
Appeals
Monmouth County Construction Board of Appeals

Summary

In Howell Township, electrical work is priced under the electrical subcode fee schedule in § 139-86C of the Township Code. The base fee is $75 for 1 to 50 receptacles, fixtures and switches, and the minimum fee is $85 for R-3 and R-5 use groups and $150 for all other use groups.

C. Electrical subcode fees. (1) Electrical fixtures and devices. ... Items Fee 1 to 50 receptacles, fixtures, and switches $75 Increments of 25 additional items $15 ... (3) Service equipment (service panel, service entrance, and subpanels). Each piece of equipment shall be priced as follows: Size (amps) Fee Greater than 0 but less than or equal to 200 $75 Greater than 200 but less than or equal to 1,000 $200 Greater than 1,000 $500 (4) Temporary service/pole. Service plus GF receptacle: $90. ... (9) Minimum fee. The minimum fee for electrical subcode plan review and/or inspections for R-5 and R-3 shall be $85; all other use groups: $150.

Full Breakdown

The Township Council set the electrical subcode schedule in Howell Township Code § 139-86C, and Chapter 108 points every Uniform Construction Code fee to Chapter 139. Fixture work is counted in items: the code defines "receptacles," "fixtures," and "switches" to include lighting outlets, fluorescent fixtures, light standards, pool bonding, intercom devices, telephone outlets, thermostats, burglar alarm devices, heat detectors and smoke detectors. The first block of 1 to 50 items costs $75, and each increment of 25 additional items costs $15.

Service equipment is priced per piece: $75 up to and including 200 amps, $200 above 200 and up to 1,000 amps, and $500 above 1,000 amps. A temporary service or pole with a GF receptacle is $90, and an average residential central air unit or air handler plus disconnect is $65. Motors are priced by horsepower, from $25 for a motor greater than 1 but not more than 10 horsepower up to $500 above 100 horsepower. Aboveground pools are $75 with one pump motor plus $20 for each additional pump motor. In-ground pools are $120 with one pump motor plus $25 for each additional one, with pool lights and pool heaters at $25 each. An annual commercial in-ground pool inspection is $75.

The code also lists typical kilowatt ratings for appliances such as an electric dryer, range, oven and water heater, and the actual nameplate KW rating must be on the application to avoid a delay in permit issuance.

Process and appeals come from Chapter 108. The Construction Office in Howell Township includes a Construction Official and an Electrical Subcode Official, and the public does business with it at the Municipal Building, Preventorium Road, Howell, New Jersey 07731. Appeals from its decisions go to the Monmouth County Construction Board of Appeals under § 108-2.

Violations & Fines

Chapter 108 prints no fine schedule of its own. It creates the Construction Office under § 108-1, routes every fee amount to Chapter 139 under § 108-3, and sends appeals from Construction Office decisions to the Monmouth County Construction Board of Appeals under § 108-2.

Frequently Asked Questions

What is the minimum electrical permit fee in Howell Township?
Under Howell Township Code § 139-86C(9), the minimum fee for electrical subcode plan review and inspections is $85 for R-5 and R-3 use groups. Every other use group pays a minimum of $150. The minimum applies even when the itemized fees add up to less.
How is a temporary electrical pole priced in Howell Township?
A temporary service or pole is $90, described in the code as service plus GF receptacle. That fee sits in § 139-86C(4) and is separate from the service equipment tiers of $75, $200 and $500 that apply to panels, service entrances and subpanels based on amperage.
Where do I appeal an electrical subcode decision in Howell Township?
Section 108-2 of the Township Code names the Monmouth County Construction Board of Appeals as the body that hears appeals from decisions of the Howell Township enforcing agency. The enforcing agency is the Construction Office, which includes the Construction Official and the Electrical Subcode Official under § 108-1.
Does the Township code set a fee for pool electrical work?
Yes. An aboveground pool is $75 with one pump motor and $20 for each additional pump motor. An in-ground pool is $120 with one pump motor and $25 for each additional one. Pool lights and pool heaters are $25 each, and an annual commercial in-ground pool inspection is $75.

Sources & Official References

Other rules in Howell

All Howell rules

Compare Howell to another location·View the New Jersey building safety overview

Get notified when Electrical Permits in Howell, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in this county handle electrical permits.

Long Branch, NJ
Some Restrictions