Medford, OR Building Safety: Electrical Permits (2026)
Key Facts
- Adopted code
- Oregon Electrical Specialty Code
- Permit expiration
- 180 days of inactivity
- Governing sections
- Medford Code §§ 9.250, 9.251
- Unpermitted work penalty
- Investigative fee plus permit fee
- Disconnection authority
- Building Safety Director
Summary
Medford adopts the Oregon Electrical Specialty Code under Section 9.250 and requires a permit before any new electrical installation under Section 9.251. Permits lapse after 180 days of inactivity, and the Building Safety Director can disconnect power on installations completed without required approval.
Duly issued Electrical Permits shall expire after 180 days of inactivity on the work for which the electrical permit is issued. A new permit may be required in the event that the work is to commence after the permit has expired. ... Except as provided in ORS 479.540, no person shall work on any new electrical installation for which a permit has not been issued.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-32, passed May 6, 2026).
Full Breakdown
250 adopts "the current version of the Oregon Electrical Specialty Code as published by the National Fire Protection Association and as modified by the Director of the State Department of Business and Consumer Services" as Medford's Electrical Code, with the Building Safety Director acting as the "Administrator" or "department" referenced in the code text. 251 then sets Medford-specific permit rules: an issued Electrical Permit "shall expire after 180 days of inactivity on the work for which the electrical permit is issued," after which a new permit may be required to resume work.
540 allows, and subsection (2) adds an investigative fee, on top of the regular permit fee, for anyone who knowingly does electrical work without first obtaining a permit. 250(3) gives the Building Safety Director direct disconnection authority over any electrical installation connected in violation of the code or before approval for service has been given, requiring the Director to post a notice at the premises stating the wiring was disconnected for noncompliance, and it is unlawful to reconnect afterward without authorization. 251(4).
Violations & Fines
Working without a required electrical permit draws an investigative fee under Section 9.251(2) on top of standard permit fees, and it is a separate violation to keep an installation energized after the Building Safety Director has disconnected it or ordered disconnection under Section 9.250(3). Broader Building Code violations follow Section 9.660's civil penalty track: up to $5,000, or $1,000 per day continuing, appealable to the Unified Appeal Board within ten business days.
Frequently Asked Questions
Do I need a permit for electrical work in Medford?
How long is a Medford electrical permit valid?
What happens if I do electrical work without a permit?
Sources & Official References
Other rules in Medford
Compare Medford to another location·View the Oregon building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.