Modesto, CA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Adopted code
2025 California Electrical Code (Title 24, Part 3)
Latest amendment
Ord. 3810-C.S., effective June 11, 2026
Enforcing official
Building Official, Building Safety Division
Permit lifetime
Lapses at 180 days unstarted or 730 days unfinished
Temporary power
Up to 30 calendar days before final inspection
Criminal penalty
Misdemeanor: up to $1,000 and six months in jail
Appeal deadline
30 calendar days from service of the notice

Summary

Modesto adopts the 2025 California Electrical Code (California Code of Regulations Title 24, Part 3, published by the NFPA) as the city's Electrical Code under § 9-3.101. Ordinance 3810-C.S. moved the reference up from the 2022 edition effective June 11, 2026. Electrical work needs a permit from the Building Official unless Chapter 3 exempts it, and violations are misdemeanors.

That certain document, one (1) copy of which is on file in the Office of the Chief Building Official of the City of Modesto, being marked and designated as the 2025 California Electrical Code, California Code of Regulations Title 24, Part 3, as published by the National Fire Protection Association (NFPA), as now existing, or hereafter amended, regulating, governing and providing standards for the erection, installation, repair, relocation, replacement, addition to, use, or maintenance of electrical systems and parts thereof for the protection of public health and safety, providing for the issuance of permits and collection of fees, providing penalties for the violation thereof; and each and all of the regulations, provisions, penalties, conditions and terms of said 2025 California Electrical Code on file in the Office of the Chief Building Official of the City of Modesto is hereby referred to, adopted and made a part hereof, as if fully set out in this ordinance, with the additions, deletions, insertions, and changes if any, prescribed in this Chapter, be and hereby is adopted as the Electrical Code of the City of Modesto.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 71).

Full Breakdown

Section 9-3.101 incorporates the 2025 California Electrical Code by reference, "as now existing, or hereafter amended," so Modesto's electrical rules follow the state's Title 24, Part 3 text published by the National Fire Protection Association instead of a separate local rewrite. One copy sits on file in the Office of the Chief Building Official. Ordinance 3810-C.S., effective June 11, 2026, replaced the 2022 edition named in the section and in the Article 1 title. Earlier adoption cycles took effect on January 3, 2008, January 13, 2011, January 3, 2014, January 6, 2017, December 26, 2019 and January 24, 2023. Under § 9-3.204 the code's appendices stay out unless the State Building Standards Commission or the city adopts them.

Anyone who intends to erect, install, enlarge, alter, repair, remove, convert or replace a regulated installation must first apply to the Building Official and obtain a permit (§ 9-3.501). The exemptions in § 9-3.502 are narrow: cord-and-plug portable appliances, like-for-like replacement of fixed motors, transformers or overcurrent devices in the same location, taping joints, removing wiring, temporary decorative lighting up to 90 days, wiring below 25 volts that cannot supply more than 50 watts, and Class II and III low-energy circuits. Emergency repairs need the application and permit by the next business day (§ 9-3.503).

Applications must describe the work and the site and state its valuation, and the Building Official can require electrical schematics, load calculations and wire sizes (§ 9-3.603). An application with no permit issued within 180 calendar days expires. An issued permit lapses if work does not start within 180 days, stops for 180 days, or is unfinished after 730 calendar days, with one extension of up to 180 days on written request (§ 9-3.510).

Fees follow a City Council fee schedule (§ 9-3.702). Starting work before the permit adds a fee under § 9-3.703, and an investigation fee equal to the permit fee applies under § 9-3.705. No system can be covered, concealed or put into use before inspection (§ 9-3.804). Utility power waits for the Building Official's release and a passed final inspection, and a temporary connection runs no longer than 30 calendar days (§§ 9-3.901, 9-3.902).

Violations & Fines

Violating the Electrical Code is a misdemeanor under § 9-3.1118: a fine of up to $1,000, up to six months in county jail, or both. The City Attorney can charge it as an infraction instead, at up to $250 for a first conviction and up to $500 for a repeat within one year. Each day of violation counts as a separate offense. The Building Official can also issue a notice of violation, a stop work order under § 9-3.1201, and administrative penalties under Title 1, Chapter 6. Defying a final order is itself a misdemeanor (§ 9-3.1115).

Frequently Asked Questions

Which electrical code does Modesto enforce?
Modesto enforces the 2025 California Electrical Code, which is California Code of Regulations Title 24, Part 3, as published by the National Fire Protection Association. Section 9-3.101 adopts it by reference, including later amendments, and Ordinance 3810-C.S. updated the reference from the 2022 edition effective June 11, 2026. A copy is kept at the Office of the Chief Building Official.
Which electrical jobs in Modesto do not need a permit?
Section 9-3.502 exempts cord-and-plug portable appliances, like-for-like replacement of fixed motors, transformers and overcurrent devices in the same location, taping joints, removing wiring, decorative lighting for up to 90 days, wiring under 25 volts and 50 watts, and Class II and III low-energy circuits. Exempt work must still follow the code and every other law.
How long does a Modesto electrical permit last?
A permit becomes null and void if work does not start within 180 calendar days of issue, if work stops for 180 calendar days, or if the job is unfinished 730 calendar days after issue. The Building Official can grant one extension of up to 180 days on a written request showing circumstances beyond your control. Restarting after a lapse costs half a new permit fee if plans are unchanged and the pause was under a year.
When can the power be connected after electrical work?
Under § 9-3.901, no one can connect a utility source to a building needing a permit until the Building Official releases it, and the building must pass final inspection first. Section 9-3.902 allows a temporary connection for up to 30 calendar days if the service is judged safe. After that, the Building Official can ask the utility to disconnect.
How do I appeal a Building Official decision on electrical work?
File a written appeal with the Building Official within 30 calendar days of service of the notice or of the action, and pay the appeal fee set by City Council resolution. The five-member Board of Building Appeals hears it 10 to 45 days after filing. A Board decision can be challenged in court under Code of Civil Procedure sections 1094.5 and 1094.6 within 30 calendar days of service.

Sources & Official References

Other rules in Modesto

All Modesto rules

California rules heatmap·Compare Modesto to another location·View the California building safety overview

Get notified when Electrical Permits in Modesto, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.