Tigard, OR Building Safety: Electrical Permits (2026)
Key Facts
- Permit rule
- Separate permit for each separate building or structure
- Issued by
- The building official
- Plan review
- Required, per OAR 918-311-0000 through 0060
- Plan review expiry
- 180 days after application, one extension up to 180 days
- Work without a permit
- Investigation fee equal to the permit fee
- Maximum penalty
- $5,000 per offense; $1,000 per day if continuing
Summary
In the City of Tigard, Oregon, no electrical work can be performed without a separate electrical permit for each separate building or structure, obtained first from the building official. Plan review is required, fees are set by City Council resolution, and starting without a permit adds an investigation fee equal to the permit fee.
A. Permit Required. ... Except as permitted by OAR 918-261-0000 through 0039, electrical work exempt from permit, subsection O of this section for minor installations, subsection P of this section for temporary electrical permits and subsection Q of this section for industrial plant electrical permits, no electrical work shall be performed unless a separate electrical permit for each separate building or structure has first been obtained from the building official. ... E. Plan Review Requirements. Electrical plan reviews shall be required. Plan review requirements and procedures shall be as stipulated in OAR 918-311-0000 through 0060. ... G. Permit Fees. Fees for electrical permits shall be established by resolution of the city council. ... 2. Fee. ... An investigation fee, in addition to the permit fee, shall be collected whether or not a permit is then or subsequently issued. The investigation fee shall be equal to the amount of the permit fee that would be required by this code if a permit were to be issued.
Full Breakdown
Tigard Municipal Code § 14.04.065 is the city's electrical program. Subsection A makes the permit the starting point: no electrical work is performed unless a separate electrical permit for each separate building or structure has first been obtained from the building official. The exceptions are the ones the section itself names: work exempt under OAR 918-261-0000 through 0039, minor installations (subsection O, using minor installation labels under OAR 918-050-0500 through 0520), temporary electrical permits (subsection P, OAR 918-309-0080) and industrial plant electrical permits (subsection Q, OAR 918-309-0100). Section 14.04.030 adopts the Electrical Specialty Code as one of the state specialty codes the City of Tigard administers under ORS 455.150.
Electrical plan review is mandatory under subsection E, with procedures set by OAR 918-311-0000 through 0060. An application with no permit issued within 180 days expires, and the building official can extend that once, by not more than 180 days, if the applicant shows circumstances beyond their control; after expiration the applicant resubmits plans and pays a new plan review fee. Permits themselves expire under OAR 918-309-0000(7). Fees for electrical permits are set by resolution of the City Council.
Refunds are capped. The building official can refund an erroneously paid fee, not more than 80% of the permit fee when no work has been done, and not more than 80% of the plan review fee when an application is withdrawn before review effort is spent, but only on written application filed within 180 days of payment. Issuing a permit does not approve any violation of the code, and the building official can suspend or revoke a permit issued in error or on incorrect information. The official can enter a building at reasonable times to inspect after presenting credentials, disconnect service in an emergency, and order defective equipment removed or restored under a written notice with a fixed time limit.
Violations & Fines
Starting electrical work without a permit triggers a special investigation before any permit issues, and an investigation fee equal to the permit fee is added on top of it whether or not a permit is later issued (§ 14.04.065(H)). Under § 14.04.090(D) and (E), installing or altering electrical equipment contrary to Chapter 14.04 carries an administrative civil penalty of not more than $5,000 per offense or not more than $1,000 for each day of a continuing offense. The building official can serve a written stop order, and no one can reconnect power to equipment ordered disconnected until permits and inspections are approved.
Frequently Asked Questions
Does a homeowner need an electrical permit in the City of Tigard?
What happens if electrical work starts before the permit is issued?
How long does an electrical permit application stay open in Tigard?
Can the City of Tigard cut power to a building?
Sources & Official References
Other rules in Tigard
Compare Tigard to another location·View the Oregon building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.