Key Facts

Enforcing official
Electrical Subcode Official, Division of Construction Code
First 20 receptacles and fixtures
$70
Each additional 20
$10
Service panel up to 200 amperes
$140
Minimum electrical fee
$70
Plan review
25% of the construction permit amount

Summary

In Wayne Township, New Jersey, electrical work is permitted and priced under the Electrical Subcode fee schedule in § 64-2 of the Township Code. The first 20 receptacles and fixtures cost $70, service panels start at $140, and the minimum electrical fee is $70. The Electrical Subcode Official in the Division of Construction Code enforces it.

(5) Electrical Subcode fees. The electrical subcode fees shall be as follows: Type of Device or Service Fee Receptacles and fixtures First 20 $70 Each additional 20 $10 ... Service panels, entrances and subpanels and EV Chargers Up to 200 amperes $140 300-400 amperes $210 800-1,000 amperes $250 ... Minimum fee $70 Replacement of existing furnace $70 Commercial pool annual inspection $140 Generator annual inspection $140 Bonding private pool/spa/hot tub $100 (a) The fee for fixtures and devices to be counted for these items include outlets, wall switches, fluorescent fixtures, convenience receptacles or similar fixtures and motors and devices of one horsepower or one kilowatt or less as follows: (1) First 20, fee is: $70. (2) Increments of 20, fee is $10.

Full Breakdown

The Electrical Subcode Official is one of the positions the Township Council established in § 64-1 within the Division of Construction Code, headed by the Construction Official. Under § 64-2(A) the construction permit fee, which includes the electrical subcode fee, must be paid before a permit can be issued.

The electrical schedule in § 64-2(A)(5) charges $70 for the first 20 receptacles and fixtures and $10 for each additional 20. Fixtures and devices counted for those items include outlets, wall switches, fluorescent fixtures and convenience receptacles, along with motors and devices of one horsepower or one kilowatt or less. Service panels, entrances, subpanels and EV chargers are $140 up to 200 amperes, $210 for 300-400 amperes and $250 for 800-1,000 amperes. Motors and electrical devices are $70 to 10 horsepower, $140 to 50 horsepower, $210 to 100 horsepower and $806 above 100 horsepower. Photovoltaic systems are $91 to 50 kilowatts, $180 to 100 kilowatts and $896 above 100 kilowatts.

The schedule also prints $70 for replacement of an existing furnace, $140 for a commercial pool annual inspection, $140 for a generator annual inspection and $100 for bonding a private pool, spa or hot tub. A pool with underwater lights is $100 and a storage pool or spa is $70. Reconnecting electrical power carries a minimum fee of $75.

Plan review adds 25% of the amount charged for the construction permit. For condominium and cooperative units, § 64-2(E) bars an electrical permit for work causing exterior changes unless the homeowners' association certifies its approval, in every case where its bylaws require approval. Chapter 64 prints fees and staffing only; it does not reprint an electrical code.

Violations & Fines

Chapter 64 has no penalty clause of its own, so the general penalty in § 1-15.1 of the Wayne Township Code applies: on conviction, up to 90 days in the County Jail or other place of detention, a fine not exceeding $2,000, or community service not exceeding 90 days. A repeat offender convicted within one year of a prior violation faces an additional fine under § 1-15.4.

Frequently Asked Questions

How much does an electrical permit cost for a panel upgrade in Wayne Township?
Under § 64-2(A)(5), service panels, entrances, subpanels and EV chargers cost $140 up to 200 amperes, $210 for 300-400 amperes and $250 for 800-1,000 amperes. The electrical minimum fee is $70, and the fee must be paid before the permit is issued.
Does an EV charger need an electrical permit in Wayne?
The fee schedule lists EV Chargers in the same row as service panels, entrances and subpanels, so the charger is priced by amperage: $140 up to 200 amperes, $210 for 300-400 amperes and $250 for 800-1,000 amperes. Chapter 74 of the Code separately covers electric vehicle supply equipment.
What is charged for a pool or spa electrical inspection?
Bonding a private pool, spa or hot tub is $100. A pool with underwater lights is $100 and a storage pool or spa is $70. A commercial pool annual inspection is $140, and a generator annual inspection is also $140.
Who inspects electrical work in Wayne Township?
The Electrical Subcode Official inspects it, a position set up in § 64-1 inside the Division of Construction Code. The Construction Official heads the Division and reports to the Department of Public Works. An on-site inspection agency can be retained by contract in place of a particular subcode inspector.

Sources & Official References

Other rules in Wayne

All Wayne rules

Compare Wayne to another location·View the New Jersey building safety overview

Get notified when Electrical Permits in Wayne, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Passaic County handle electrical permits.

Paterson, NJ
Some Restrictions