Key Facts

Permit required before
any electrical wiring or equipment installation
Issuing agency
Dept. of Planning, Zoning and Community Development
Residential permit fee
$35 per permit
Commercial permit fee
$70 per permit
Inspection turnaround
within 7 work days of request
Standard adopted
National Electrical Code + County Electrical Code
Max civil infraction fine
$1,000 per violation

Summary

Unincorporated Wicomico County requires a permit from the Department of Planning, Zoning and Community Development before any electrical work begins, and all installations must meet the National Electrical Code as adopted locally. Only registered electricians may pull the permit except for narrow owner-occupant exceptions.

These county ordinances apply to unincorporated areas of Wicomico County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any person permitted to install electrical work must first secure a permit to do so from the Wicomico County Department of Planning, Zoning and Community Development before starting any such work. ... ... D. The Board shall adopt as standards for the installation of electrical work, apparatus and devices of all kinds, those required from time to time by the National Electrical Code and Wicomico County Electrical Code; all material and equipment must be approved by the Underwriters' Laboratories, Inc., or other accredited authoritative agency and testing organizations.

Full Breakdown

Under Wicomico County Code Ch. 138, anyone doing electrical work in unincorporated Wicomico County must first secure a permit from the Department of Planning, Zoning and Community Development before starting any wiring, conduit, machinery, apparatus or fixture installation (§ 138-24B). A temporary service pole permit must fold in whatever permanent installation the project ultimately needs. Separate permit fees apply to commercial and residential electrical work, set by the Board of Electrical Examiners and approved by the County Council; the fee schedule in Ch. 141 lists electrical permits under §§ 138-24B and 117-5 at $70 per commercial permit and $35 per residential permit.

The Electrical Examiners Board adopts as its installation standard the National Electrical Code together with the Wicomico County Electrical Code, and requires all material and equipment to carry Underwriters' Laboratories or equivalent accredited-agency approval (§ 138-24D). Inspections must be performed by inspectors registered with the Board within seven working days of an inspection request, and no power company may connect current to a property without a cut-in card from an approved inspector, except in an emergency where a licensed contractor may restore service ahead of the card (§ 138-24C).

1). A narrow owner-occupant exemption lets a bona fide owner do wiring in a single-family dwelling they will occupy for six months, but the § 138-24 permit and inspection duties still apply (§ 138-23A(3)).

Violations & Fines

A permit or inspection violation under Ch. 138 is a civil infraction carrying a fine of up to $1,000 per violation, set by a fine schedule the County Council adopts by resolution (§ 138-25A). The Director of Planning, Zoning and Community Development or a designee issues the citations, and the Chief Building Inspector enforces the Electrical Code, ordering corrections or assessing fines after investigating complaints (§ 138-25B). Each day a violation continues is a separate offense, and the County may also seek an injunction in Circuit Court to stop unlawful work or prevent occupancy of a noncompliant structure (§ 138-25C). The County Department of Law prosecutes the civil infractions (§ 138-25D).

Frequently Asked Questions

Do I need a permit for electrical work on my unincorporated Wicomico County home?
Yes. Wicomico County Code § 138-24B requires anyone doing electrical work to first secure a permit from the Department of Planning, Zoning and Community Development before starting, with separate fees set for residential and commercial jobs.
Can I do my own wiring without a license?
Only if you are the bona fide owner-occupant of a single-family dwelling you will live in for six months after the work is done and you buy the materials and do all the labor yourself; the § 138-24 permit and inspection duty still apply, per § 138-23A(3).
What code does Wicomico County use for electrical installations?
Section 138-24D directs the Board of Electrical Examiners to adopt the National Electrical Code and the Wicomico County Electrical Code as the installation standard, and requires equipment to carry Underwriters' Laboratories or equivalent approval.
What happens if I skip the electrical permit?
It is a civil infraction under § 138-25A punishable by a fine of up to $1,000 per violation, with each day of continued violation counted separately, and the county's Chief Building Inspector can order corrections or issue citations.

Sources & Official References

Other rules in Wicomico County

All Wicomico County rules

Compare Wicomico County to another location·View the Maryland building safety overview

Get notified when Electrical Permits in Wicomico County, MD changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.