Albany, OR Building Safety: Building Inspections (2026)
Key Facts
- Inspecting authority
- Albany building official, Building Division
- Governing section
- Albany Municipal Code § 18.08.010
- Advance notice
- Building official can require 2 working days
- Covering work
- Barred until approved for that stage
- Temporary certificate of occupancy
- No more than 180 days without approval
- Concealed work
- Must be exposed at the owner's cost
Summary
In the City of Albany, Oregon, permitted work stays exposed and accessible until the building official approves each stage, and nothing may be covered before sign-off. Albany Municipal Code § 18.08.010 sets that rule, and the permit holder must request every inspection.
(1) Construction or work for which a permit is required shall be subject to inspection by the building official and the construction or work shall remain accessible and exposed for inspection purposes until approved by the building official. No work shall be covered until approved and signed off for that stage of the project or work. In addition, certain types of construction shall have special or continuous inspection as specified in the Oregon Building Code. ... (5) A survey of the lot may be required by the building official to verify that the structure is located in accordance with the approved plans.
Full Breakdown
Chapter 18.08 of the Albany Municipal Code controls inspections. Section 18.08.010(1) subjects all permitted construction to inspection by the building official and requires the work to remain accessible and exposed until approved. No work is covered until it is approved and signed off for that stage. Certain construction also needs special or continuous inspection as the Oregon Building Code specifies. The building official can require a survey of the lot to confirm the structure sits where the approved plans put it (section 18.08.010(5)).
Requesting inspections is the permit holder's job. Section 18.08.020 makes the person doing the work notify the building official that the work is ready, provide access during normal business hours, and supply ladders, walkways, lighting, and carpet runners for safe access. The building official can require each request to be filed at least two working days before the inspection is wanted. The permit holder cannot proceed with construction activity until authorized by the building official. Section 18.08.030 ties the required inspections to the Oregon Building Code, and section 18.08.070 adds special inspections by a special inspector the building official approves in advance.
Section 18.08.080 stops work at each inspection point: work cannot go beyond the point indicated in each successive inspection without approval, and failed portions must be corrected and left uncovered until authorized. Final inspections must be requested and passed for each permit before anyone asks for occupancy or use. Section 18.08.090 then requires a certificate of occupancy before use, except for exempt work and residential accessory buildings. A temporary certificate can run no more than 180 days unless the building official approves more time.
Reinspection fees can be assessed under section 18.08.040 when work is incomplete, corrections are not made, plans are not on site, or access is not provided, and no further inspection happens until the fees are paid unless the building official authorizes it. Approval never excuses a violation (section 18.08.010(2)).
Violations & Fines
Section 18.08.100 requires work performed without approval to be exposed for inspection, and the permittee or owner pays for damage such as repair to sheet-rock, masonry, concrete, and siding, plus any investigation or penalties. Section 18.10.210 sets civil penalties up to $1,000 per violation for a first offense, $2,500 for a second within 3 years, and $5,000 for later ones. Occupying a building without a certificate of occupancy can bring a notice of noncompliance recorded with the county recorder.
Frequently Asked Questions
Who requests building inspections in Albany, Oregon?
How much notice does the City of Albany, Oregon need for an inspection?
Can work be covered before the Albany inspection?
When are reinspection fees charged in Albany?
Sources & Official References
Other rules in Albany
Compare Albany to another location·View the Oregon building safety overview