Auburn, WA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Rough-in inspection
Mechanical, gas, plumbing, electrical before covering
Envelope inspections
Wall insulation, glazing, roofing, slab (4 stages)
Special inspections
Building official may order, no city cost
Utility connection rule
No hookup until rough-in approved
Penalty for violation
Up to 90 days jail, $1,000 fine

Summary

Auburn's building official inspects construction in defined stages under ACC 15.07.090: a combined rough-in inspection for mechanical, gas, plumbing and electrical work before it is covered, a four-part energy-efficiency envelope inspection, and special inspections the official can order beyond IBC Chapter 17 requirements.

The city will conduct inspections as prescribed in the latest adopted copy of the International Building Code with the exceptions as noted below: A. IMC/UPC/IFGC/NEC Rough-In Inspection. Rough-in mechanical, gas piping, plumbing and electrical shall be inspected when the rough-in work is complete and under test. No connections to primary utilities shall be made until the rough-in work is inspected and approved. B. Energy Efficiency Inspection – Envelope. 1. Wall Insulation Inspection. To be made after all wall insulation and air vapor retarder sheet or film materials are in place, but before any wall covering is placed. 2. Glazing Inspection. To be made after glazing materials are installed in the building. 3. Exterior Roofing Insulation. To be made after the installation of the roof insulation, but before concealment. 4. Slab/Floor Insulation. To be made after the installation of the slab/floor insulation, but before concealment.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 7023, passed July 6, 2026).

Full Breakdown

090 sets Auburn's inspection sequence on top of what the International Building Code otherwise requires. ' Subsection B breaks the energy-efficiency envelope inspection into four checkpoints: wall insulation, inspected after insulation and any air/vapor retarder sheet or film is in place but before wall covering goes on; glazing, inspected after installation; exterior roofing insulation, inspected after installation but before concealment; and slab or floor insulation, inspected after installation but before concealment. Subsection C lets the building official require special inspections beyond Chapter 17 of the International Building Code, performed by an approved agency at no cost to the city. 140, including misdemeanor prosecution for unpermitted or uninspected work.

Violations & Fines

Covering rough-in work, insulation, or glazing before the required inspection is approved, or connecting to primary utilities before rough-in sign-off, violates ACC 15.07.090 and is enforced under ACC 15.07.140(E) as a misdemeanor punishable by up to 90 days in jail and a $1,000 fine absent a more specific penalty, with the building official able to withhold a certificate of occupancy until the work is corrected.

Frequently Asked Questions

What inspection stages does Auburn require for a new home?
ACC 15.07.090 requires a rough-in inspection of mechanical, gas, plumbing and electrical work before it is covered or connected to utilities, plus four energy-efficiency envelope inspections covering wall insulation, glazing, roofing insulation and slab or floor insulation, each timed to occur before the material is concealed.
Can Auburn require inspections beyond what the International Building Code lists?
Yes. ACC 15.07.090(C) authorizes the building official to require special inspections in addition to those already listed in Chapter 17 of the International Building Code, performed by an approved inspection agency and at no cost to the city.
What happens if I cover insulation before it's inspected in Auburn?
You risk enforcement under ACC 15.07.140 as a misdemeanor, and the building official can withhold the certificate of occupancy required under ACC 15.07.100 until the concealed work is opened up, corrected and reinspected.

Sources & Official References

Other rules in Auburn

All Auburn rules

Compare Auburn to another location·View the Washington building safety overview

Get notified when Building Inspections in Auburn, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities