Granville County, NC Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Inspection stages
7, footing through certificate of occupancy
Request method
Call county inspection department office
Concealed work
Must be uncovered for inspection on request
Occupancy
Barred until certificate of occupancy issued
Enforcing agency
Granville County Inspection Department
Temporary CO
Available for safely occupiable portion

Summary

Granville County's inspection department must approve construction at each of seven defined stages before work continues, from footing and under-slab inspections through framing, insulation, and final certificate of occupancy. Permit holders must call for each inspection, and skipping a required stage or building past it without approval is itself a code violation.

These county ordinances apply to unincorporated areas of Granville County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Sec. 14-44. - Inspection procedure. (a)Inspections. ... (3)All holders of permits or their agents shall notify the inspection department and the appropriate inspector at each of the following stages of construction so that approval may be given before work is continued:a.Footing inspection, to be made after the trenches are excavated, all grade stakes are installed, all reinforcing steel and supports are in place and appropriately tied, all necessary forms are in place and braced and before any concrete is placed. ... d.Rough-In inspection, when all building framing and parts of the electrical, plumbing, or heating-ventilation or cooling system that will be hidden from view in the finished building have been placed but before any wall, ceiling finish or building insulation is installed. ... g.Certificate of occupancy final inspection, to be made after all the certificate of compliance inspections for each trade are complete, and other local laws are complied with, but before occupancy.

Full Breakdown

Sec. 14-44(a) requires the inspection department to inspect every building, structure, and permitted work as often as necessary to confirm compliance, and lets it accept certified reports from approved outside inspection organizations for materials tested at the point of manufacture. Subsection (a)(3) then lists the stages permit holders must call in for: footing inspection after trenches, grade stakes, reinforcing steel, and forms are placed but before concrete pours; under-slab inspection after electrical, plumbing, heating, and vapor-barrier work is in but before concrete; foundation inspection for wood-frame construction; rough-in inspection once framing and hidden electrical, plumbing, or HVAC work is placed but before wall or ceiling coverings go up; a building-framing inspection with pipes, chimneys, flashing, and lintels visible; an insulation inspection after framing and rough-in approval but before covering; and a final certificate-of-occupancy inspection after every trade's compliance inspection is complete.

Sec. 14-44(b) requires the permit holder to request each inspection from the inspection department office, and any concealed work not yet inspected must be uncovered on request. Sec. 14-44(d) bars occupancy of any new, altered, or moved building until the inspection department issues a certificate of occupancy, though a temporary certificate can cover a safely occupiable portion before full completion.

Violations & Fines

Sec. 14-44(b)(2) makes failing to call for a required inspection, or proceeding with construction without inspector approval at any listed stage, a violation of chapter 14 in its own right. Violations are enforced under the Code's general penalty, Sec. 1-6: a civil citation orders the violator to appear before the county finance officer within 15 days or pay by mail, with a separate citation issued for each day the violation continues. Occupying a building before the inspection department issues the required certificate of occupancy under Sec. 14-44(d) is likewise a violation, and inspectors can issue a stop-work order under Sec. 14-46(c) for hazardous work.

Frequently Asked Questions

What inspection stages does Granville County require during construction?
Sec. 14-44(a)(3) lists footing, under-slab, foundation (for wood-frame work), rough-in, building framing, insulation, and a final certificate-of-occupancy inspection. The permit holder must call the inspection department before proceeding past each stage so an inspector can approve the work first.
Can I cover up framing before the inspector sees it?
No. Sec. 14-44(a)(3)(e) requires pipes, chimneys, flashing, insulation baffles, and bolted lintels to remain visible for the framing inspection, and Sec. 14-44(b)(2) requires any concealed work to be uncovered again at the inspector's request if it wasn't inspected first.
When can I legally occupy a new building in unincorporated Granville County?
Not until the inspection department issues a certificate of occupancy under Sec. 14-44(d), confirming the building meets chapter 14, the adopted regulatory codes, and the applicable zoning. A temporary certificate may cover a portion that's safe to occupy before the whole project is finished.

Sources & Official References

Other rules in Granville County

All Granville County rules

Compare Granville County to another location·View the North Carolina building safety overview

Get notified when Building Inspections in Granville County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.