Key Facts

Rough-in inspection
Applied for before work is covered
Sewer inspection
Applied for before sewer covered
Final inspection
After all fixtures complete
Test standard
10-ft water head, no leakage
Water turn-on
Requires certificate of inspection
Enforcement
Plumbing inspector, Sec. 3-74

Summary

Gulfport's plumbing article sets out the exact inspection stages a permit holder must schedule: applications for rough-in, sewer and final inspection, each filed with the plumbing inspector before the work is covered or used, followed by a required pressure test and a certificate of inspection before water service is connected.

(a)Applications for inspections must be filed at the office of the inspector of plumbing by the plumber, on blanks, furnished by the city.(b)Applications for roughing-in inspections must be made when roughing-in is complete and this includes water supply, unless same is exposed on walls or ceilings, and before any of the work is covered up or made inaccessible to the inspector.(c)For sewer inspections applications must be made, stating time when sewer will be complete and before same is covered.(d)For final inspections application must be made when all fixtures are complete and before the house drain is connected or any portion of the system is used.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 68).

Full Breakdown

Chapter 3, Article III of the Code of Ordinances lays out the inspection sequence for plumbing work under a Gulfport permit. Sec. 3-76 requires the plumber to file separate applications, on city-furnished forms, for each inspection stage: a rough-in inspection application when roughing-in (including exposed water supply) is complete and before any work is covered or made inaccessible; a sewer inspection application stating when the sewer will be complete and before it is covered; and a final inspection application once all fixtures are complete and before the house drain is connected or any part of the system is used.

Sec. 3-78 requires that all plumbing work be tested by the plumber in the inspector's presence before acceptance, and Sec. 3-79 sets the rough-in test itself: the system must hold a column of water to the top of the pipe, with a minimum ten-foot head, without perceptible lowering, or the plumber must find and fix the leak before the inspector will approve it. Only after the work passes inspection does Sec. 3-77 require the plumbing inspector to issue a certificate of inspection, and the code is explicit that water will not be turned on or a meter set until that certificate is in the water department's hands.

Sec. 3-81 additionally bars covering any plumbing or drain work before the inspector, who must show a badge of authority on request, has inspected it.

Violations & Fines

Working without securing the required inspections, covering plumbing before it is inspected, or connecting water service without a certificate of inspection violates Article III. The plumbing inspector holds police power under Sec. 3-74 to enter buildings to check for violations and may arrest and file charges against a violator, who is subject to Sec. 1-9's general penalty: up to a $1,000 fine, 90 days' imprisonment, or both.

Frequently Asked Questions

What inspections does Gulfport require during a plumbing job?
Three separate applications: a rough-in inspection once the rough plumbing and exposed water supply are done but not covered, a sewer inspection before the sewer line is covered, and a final inspection once every fixture is installed and before the house drain is connected, per Sec. 3-76.
Can I turn the water on before the plumbing is inspected?
No. Sec. 3-77 requires the plumbing inspector to issue a certificate of inspection once the work passes, and water will not be turned on or a meter set at the premises until that certificate is in the water department's hands.
How is a rough-in plumbing test performed in Gulfport?
Sec. 3-79 requires the system to be filled with water to a minimum ten-foot head and held there without perceptible lowering; if the water level drops from a leak, the plumber must locate and fix it before the inspector will approve the rough-in.

Sources & Official References

Other rules in Gulfport

All Gulfport rules

Compare Gulfport to another location·View the Mississippi building safety overview

Get notified when Building Inspections in Gulfport, MS changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.