Skip to main content

Issaquah, WA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified November 2026

Key Facts

Governing sections
CAC 110.4.1 through 110.4.15 in IMC 16.04.010
Inspector
Building Official, designated agent or approved agency
Who requests
Permit holder or authorized agent, per 110.6
Rough-in rule
No primary utility connections until rough-in is approved
Occupancy
Not until final inspection is approved or temporary certificate conditions are met
After-hours rate
$100 per hour, 4 hour minimum per inspector, plus equipment rate

Summary

In Issaquah, the Building Official, a designated agent or an approved agency makes the inspections listed in sections 110.4.1 through 110.4.15 of the Construction Administrative Code, from footing and foundation through final. Work cannot proceed past any inspection point without the Building Official's approval, and the building cannot be occupied until final inspection is approved.

110.4 Required inspections. The Building Official, his or her designated agent, or an approved agency, upon notification, shall make the inspections set forth in Sections 110.4.1 through 110.4.15. 110.4.1 Footing and foundation inspection. Footing and foundation inspections shall be made after poles or piers are set or trenches or basement areas are excavated and all required hold-down anchor bolts, hold-down straps, any forms erected, and any required reinforcing steel is in place and supported. ... 110.4.15 Final inspection. The final inspection shall be made after all work required by the building permit is completed. The building shall not be occupied until final inspection is approved or conditions of a temporary certificate of occupancy are met. ... 110.7 Approval required. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the Building Official.

Full Breakdown

Section 110.4 of the Construction Administrative Code (IMC 16.04.010) sets the sequence. Footing and foundation inspections come after poles or piers are set or trenches or basement areas are excavated and all hold-down anchor bolts, straps, forms and reinforcing steel are in place. Concrete slab and under-floor inspections occur before any concrete is placed or floor sheathing installed. In flood hazard areas an elevation certificate for the lowest floor is submitted to the Building Official before further vertical construction (110.4.3), and exterior wall sheathing and roof sheathing are inspected after framing but before covering, with no roof coverings installed until approval.

Rough-in plumbing, mechanical, gas piping and electrical are inspected after the roof, framing, fire-blocking and bracing are complete, before fixtures are set and before the framing inspection; no connections to primary utilities may be made until the rough-in is inspected and approved. Replacement heating equipment serving an occupied portion of a structure can operate if an inspection request is filed within 48 hours after the replacement work is completed. Framing inspections follow once the building is substantially dried in. Further stages cover lath and gypsum board, weather-exposed balcony waterproofing, fire-resistance-rated construction and energy efficiency, and multiunit residential buildings need a Chapter 64.55 RCW building enclosure letter before a final certificate of occupancy.

The permit holder or authorized agent must notify the Building Official when work is ready (110.6) and keep the work visible and accessible until approved (110.1). The City is not liable for the cost of removing or replacing materials to allow inspection. Section 110.7 requires approval before work goes past each inspection point, and noncompliant portions must be corrected and not covered until authorized. Section 110.4.15 requires a final inspection after all permitted work is complete. After-hours inspections are listed at $100 per hour with a 4 hour minimum per inspector plus equipment rate.

Violations & Fines

A failed inspection means the necessary corrections must be made and the work reinspected (110.4.12). A reinspection fee can be assessed when work is not complete, earlier corrections are not made, the approved plans and permit are not on site or the building is not accessible, and the City provides no additional inspection until assessed fees are paid. Covering work before approval breaches section 110.7. A violation of the construction codes chapter is a civil violation enforced under Chapter 8.45 IMC (IMC 16.04.130), and section 109.5 adds a special investigation fee for work started before a permit.

Frequently Asked Questions

Which inspections does Issaquah require during construction?
Section 110.4 lists footing and foundation, concrete slab and under-floor, lowest floor elevation in flood areas, exterior wall and roof sheathing, rough-in plumbing, mechanical, gas and electrical, framing, lath and gypsum board, fire-resistance-rated construction, energy efficiency and final inspections. The Building Official can also require other and special inspections.
Who has to ask for an inspection?
Section 110.6 makes it the duty of the building permit holder or the holder's authorized agent to notify the Building Official when work is ready for inspection. The permit holder must also provide access to, and means for, the required inspections.
Can I cover work before it is inspected?
No. Section 110.7 says work shall not be done beyond the point indicated in each successive inspection without first obtaining the Building Official's approval, and portions that do not comply must be corrected and not covered or concealed until authorized. Section 110.1 requires the work to stay visible and accessible.
What happens when work fails inspection?
Corrections must be made and the work reinspected under section 110.4.12. A reinspection fee can be assessed, and once assessed the City will not provide additional inspection of the work until the fees are paid.
When can I move into the building?
Section 110.4.15 says the building shall not be occupied until final inspection is approved or the conditions of a temporary certificate of occupancy are met.

Sources & Official References

Other rules in Issaquah

All Issaquah rules

Compare Issaquah to another location·View the Washington building safety overview

Get notified when Building Inspections in Issaquah, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in King County handle building inspections.

Renton, WA
Some Restrictions
Kirkland, WA
Some Restrictions
Auburn, WA
Some Restrictions
Bellevue, WA
Some Restrictions