Key Facts

Required inspections
Foundation, structure, insulation, plus final
Sleeping basements
Extra inspection required before floor is poured
Failed-call fee
$25 when work isn't ready for inspection
Occupancy rule
Unlawful before final inspection and certificate issue
Enforcing office
Director, Building Inspection Division

Summary

Madison's Building Inspection Division requires three staged inspections during construction, foundation, structure and insulation, plus a basement floor inspection for sleeping space and a final inspection, under Section 29.10, MGO. Contractors must call for each inspection before work continues, and occupancy is unlawful until the final inspection and certificate of occupancy issue.

No work shall be done on any part of the building or structure beyond the point indicated in each successive inspection without first obtaining the approval of the Director of the Building Inspection Division... It shall be the responsibility of the contractor/owner to call the Building Inspection Division for all required inspections listed below:(a)Inspection of Foundations: To be made after trenches are excavated and poured and the necessary forms erected... (b)Inspection of Structure: To be made after the roof is in place; all framing, fireblocking and bracing are in place and all pipes, chimneys and vents are complete.(c)Inspection of Insulation: To be made after the insulation is in place, required vapor barrier has been installed and sealed.(d)Basement Floor Inspection: To be made if the basement is to be used for living and sleeping purposes...(e)Final Inspection: To be made after the building is completed and is ready for occupancy.

Full Breakdown

10(2), MGO bars any work from proceeding past the point covered by each successive inspection without the Director's approval, and requires the contractor or owner to call for each of the following: foundation inspection after trenches are excavated, forms erected and lot-line stakes set; structure inspection after the roof, framing, fireblocking, bracing, pipes, chimneys and vents are in place; and insulation inspection after insulation and vapor barrier are installed and sealed. A basement floor inspection is added before the floor is poured if the basement will be used for living or sleeping space, and a final inspection is required once the building is complete and ready for occupancy.

10(1), MGO separately bars covering or concealing 'reinforcing steel or structural framework of iron or steel' before the Director signs off on that portion of the work. 10(3), MGO allows the city to assess a $25 charge for that failed inspection call. 11(1), MGO.

Violations & Fines

Calling for an inspection when the work isn't ready costs $25 per failed call under Section 29.10(3), MGO. Occupying a building before the final inspection passes and a certificate of occupancy issues violates Section 29.11, MGO, and any Chapter 29 violation carries a forfeiture of $10 to $1,000 under Section 29.20(2), MGO, with each day treated as a separate offense.

Frequently Asked Questions

What inspections does Madison require during construction?
Section 29.10(2), MGO requires three staged inspections, foundation (after forms are set), structure (after framing, roofing and rough plumbing are done) and insulation (after vapor barrier is sealed), plus a final inspection before occupancy. A basement floor inspection is added if the basement will be used for living or sleeping space.
Who has to call for a Madison building inspection?
The contractor or owner must call the Building Inspection Division for each required inspection listed in Section 29.10(2), MGO. If the inspector arrives and the work isn't ready, Section 29.10(3), MGO allows the city to charge $25 for that failed inspection call.
Can I move into a new Madison building before it's inspected?
No. Section 29.10(3), MGO makes it unlawful to occupy a building, or let it be occupied, until all required inspections are complete and a certificate of occupancy has been issued under Section 29.11, MGO. Small one-story accessory buildings like sheds and garages are exempt from the certificate requirement.

Sources & Official References

Other rules in Madison

All Madison rules

Compare Madison to another location·View the Wisconsin building safety overview

Get notified when Building Inspections in Madison, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Dane County handle building inspections.

Fitchburg, WI
Some Restrictions