Key Facts
- Inspection cost
- Included in the permit fee for the completed work
- Failed inspection
- Inspector notifies contractor or owner of required corrections
- Reinspection
- Inspector reinspects once notified corrections are made
- Extra-trip triggers
- Condemned work, plan noncompliance, work not ready when called
- Permit exemption
- Repairs under $1,500 with no occupancy change
- Threshold buildings
- Special inspector; $1,000,000 professional liability insurance
Summary
In the City of Margate, Florida, the permit fee already pays for inspection of the finished work. If the inspector finds non-conforming work, corrections are ordered and the inspector reinspects. Extra trips for condemned work, plan violations or unready work are charged separately.
(2)Payment, inspection included in fees. Permit fees shall include payment for the permit and for inspection of the work for which the permit was obtained after the same shall have been completed. If, upon such inspection, the designated inspector finds that the work does not conform to or comply with the provisions of this chapter, the inspector shall notify the contractor or owner of the corrections required. When the inspector is notified that the corrections have been made, he shall again inspect the work.(3)Additional inspections. When additional inspection trips are necessary due to any one (1) of the following reasons, a charge in accordance with this section shall be made for each such trip:a.Condemned work, resulting from faulty construction;b.When work does not comply with the building code or the approved plans;c.Work not ready for inspection when called.
Full Breakdown
Section 9-21 of the Margate Code, the schedule of permit fees, is where the city describes how building inspections are paid for and repeated. Subsection (2) says permit fees include payment for the permit and for inspection of the work for which the permit was obtained after the work is completed. If the designated inspector finds that the work does not conform to or comply with the chapter, the inspector notifies the contractor or owner of the corrections required. When the inspector is told the corrections have been made, the inspector inspects the work again.
Subsection (3) covers additional inspection trips. A separate charge applies for each trip made necessary by condemned work resulting from faulty construction, work that does not comply with the building code or the approved plans, or work not ready for inspection when called. Fees for reinspection due to correction of workmanship or other violations must be paid by the permit holder before any further reinspection for that discipline is made or any further permits are issued to the person or firm owing them. The dollar amounts are not printed in the code; section 9-21 says fees are set by resolution of the city commission.
The city staffs these inspections in-house. Sections 9-1 and 9-2 create the position of building official and the positions of structural, mechanical, plumbing and electrical inspector as full-time city employees under the building official's direction, serving at the pleasure of the city commission. Section 9-21(5) exempts general maintenance or repairs that do not change occupancy and cost less than $1,500 in labor and materials, as determined by the building official.
Tall buildings follow a stricter track. Section 9-8 requires threshold buildings to be permitted and inspected as F.S. § 553.79 requires, with a special inspector who files a signed and sealed compliance certification before a certificate of occupancy issues. The owner must require that inspector to carry professional liability insurance of at least $1,000,000.
Violations & Fines
Skipping the permit is the main exposure. Section 9-21(4) charges anyone who starts work without a valid permit under the fee schedule adopted by commission resolution. Building code violations are also enforced under section 1-8: a fine not to exceed $500 and up to 60 days in jail, with each day a separate violation, or a civil citation at $75 for a first offense, $100 for a second and $150 for a third.
Frequently Asked Questions
Does the Margate permit fee cover the inspection?
What happens if my work fails inspection?
When does Margate charge for an extra inspection trip?
Do all repairs need a permit and inspection?
Sources & Official References
Other rules in Margate
Florida rules heatmap·Compare Margate to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Broward County handle building inspections.