New Britain ties the last stages of a construction project to inspection under sections 7-1, 7-10 and 7-12: a fifty dollar fee applies every time a trade inspector is called back for a final reinspection on jobs over five thousand dollars, and the certificate of occupancy cannot issue until costs are verified and, where applicable, public works confirms sidewalk repairs.
The fees for final reinspection for construction over five thousand dollars ($5,000.00) shall be fifty dollars ($50.00) for each trade inspector called for reinspection. This fee shall apply each time an inspector is called for a final reinspection. ... When the job is completed, the chief building official may request proof of the total construction cost done under all approved permits, and the owner, agent, or contractor shall furnish an affidavit of the total construction costs to the chief building official. If the final cost exceeds the fee declared in the application for the building permit, certificate of occupancy can not be issued until additional fee has been paid to the department. ... Before a certificate of occupancy can be issued by a chief building official, the department of public works shall submit a report verifying that all sidewalks and curbs have been restored and/or replaced in accordance with the city standards.
Full Breakdown
Section 7-1(d) sets a fifty dollar fee for final reinspection on construction valued over five thousand dollars, charged each time a trade inspector is called back to reinspect the work. Section 7-10 lets the chief building official demand proof of total construction cost once the job is finished, requiring the owner, agent or contractor to furnish an affidavit of the actual costs; if the final cost exceeds what was declared on the permit application, the certificate of occupancy cannot be issued until the additional permit fee is paid.
Section 7-12 adds a sidewalk-specific inspection step: any permit for new construction on a lot next to an existing sidewalk requires the applicant to restore or replace defective or construction-damaged sidewalks and curbs to city standards, and before the chief building official can issue a certificate of occupancy, the department of public works must submit a report verifying that restoration was completed. Section 7-7 covers the reverse case, crediting or refunding fees for work never completed once inspection confirms the actual volume finished, after any outstanding penalties are collected.
Together these sections show the inspection sequence running from trade reinspections during construction, through a cost-verification inspection at completion, to a public works sidewalk sign-off, all gating final issuance of the certificate of occupancy by the department of licenses, permits and inspections.
Violations & Fines
A certificate of occupancy will not issue under section 7-10 until any cost overrun above the permitted value is paid, and under section 7-12 it is withheld until public works confirms sidewalk and curb restoration; each additional trade reinspection called under section 7-1(d) adds a fifty dollar fee to the project regardless of the original permit cost.
Frequently Asked Questions
What happens at final inspection for a New Britain building permit?
Does New Britain inspect sidewalks before issuing a certificate of occupancy?
Is there a fee if my New Britain project needs a second final inspection?
Sources & Official References
Other rules in New Britain