New York, NY Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing code
NYC Construction Codes Title 28
Inspection types
Preliminary, compliance, special/progress, final
Final inspection window
Within 1 year of last permit
Sign-off requires
Satisfactory final inspection report
Enforcing agency
NYC Department of Buildings

Summary

New York City's Construction Codes require four categories of Department of Buildings inspection on any permitted job, preliminary, compliance, special/progress, and final, with a satisfactory final inspection mandatory before DOB signs off with a letter of completion or certificate of occupancy.

The inspections set forth in sections 28-116.2.1 through 28-116.2.4 are required or authorized by this code... Preliminary inspection... Compliance inspections... Special inspections, progress inspections and other inspections required during the progress of work... Final inspection. There shall be a final inspection of all permitted work.

Full Breakdown

Under Administrative Code § 28-116.2, permitted construction is subject to preliminary inspections (verifying vacancy claims on 6+ unit buildings), compliance inspections at DOB's discretion, special and progress inspections performed at set stages by approved agencies or special inspectors, and a final inspection after all work is complete. Work must stay exposed and accessible for inspection, and the permit holder bears the cost of any removal or replacement needed to allow it. Per § 28-116.4, DOB issues a letter of completion or certificate of occupancy only after a satisfactory final inspection report and all submittal documents are on file, and can withhold sign-off under § 28-116.5 while fines or civil penalties on the building remain unpaid.

Violations & Fines

Uncorrected defects or hazardous conditions found at inspection must be reported in writing to the commissioner and the owner; DOB can withhold the letter of completion or certificate of occupancy until corrected, and separately refuse sign-off while outstanding fines or civil penalties on the building are unpaid.

Frequently Asked Questions

Who requests a building inspection in NYC?
The permit holder must notify DOB, or the designated inspecting agency, when work requiring inspection is ready, and must provide access under Administrative Code § 28-116.3.
Can DOB refuse to sign off my project?
Yes: under § 28-116.5, DOB may refuse a letter of completion or certificate of occupancy while any outstanding fines or civil penalties on the building remain unpaid.

Sources & Official References

Other rules in New York

All New York rules

New York rules heatmap·Compare New York to another location·View the New York building safety overview

Get notified when Building Inspections in New York, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.