Peoria, AZ Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing office
Development and Engineering Department
General duty
Keep work accessible until inspected
Pool inspections
Rough-in, then final, before filling
Re-inspection fee
Charged for incomplete/failed inspection
Unpermitted work penalty
Permit fee doubled, plus investigation fee
1-2 family exception
Final inspection + utility clearance, no CofO

Summary

Peoria's building official inspects all permitted construction under the local IBC amendments at City Code Sec. 18-21(B). Work must stay accessible and exposed until approved, swimming pools go through a rough-in and final inspection sequence, and a re-inspection fee applies when work is incomplete, plans aren't on site, or the inspector can't get access.

[A] 110.1 General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... It shall be the duty of the permit applicant to cause the work to remain accessible and exposed for inspection purposes. Neither the building official nor the jurisdiction shall be liable for expense entailed in the removal or replacement of any material required to allow inspection. [A] 109.8 Inspections and re-inspections. Permit fees provide for customary inspections only. When inspections are requested for weekends, holidays, or any time other than the regular working hours of the building official, an additional fee will be required. A re-inspection fee may be assessed for each inspection or re-inspection when such portion of work for which inspection is called is not complete or when corrections called for are not made.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-9: Supplement contains: LLocal legislation current through Ord. 2026-15, passed 6-16-26).

Full Breakdown

1 of Peoria's amended Building Code makes every permitted job subject to inspection by the building official, and the permit applicant is responsible for keeping the work accessible and exposed until it is approved; neither the building official nor the City is liable for costs of uncovering work that was concealed too soon. The building official can also require a lot survey where existing corner markers aren't verifiable. 8 lays out when extra fees apply: requesting an inspection outside regular Development and Engineering Department hours (weekends, holidays) triggers an additional fee, and a re-inspection fee is assessed whenever the called-for portion of work isn't finished, corrections weren't made, approved plans aren't available on site, access isn't provided on the scheduled date, or the work deviates from approved plans without sign-off.

1: a rough-in inspection after all fixed metal parts are bonded but before any concrete or gunite is placed, then a final inspection before finish coating and before the pool is filled, which confirms motor and electrical bonding, backflow prevention on the nearest hose bibb, and installed pool barriers. 1 before any building can be used, except that one- and two-family homes only need final inspection approval plus a utility clearance rather than a formal certificate.

Violations & Fines

Working without required permits or inspections exposes an owner to penalties under Section 114.4 plus the fees in Section 114.4.1: an investigation fee on top of the permit fee regardless of whether a permit is later issued, and a permit fee doubled for work commenced without one. The Development and Engineering Department can waive those charges only where the unpermitted work is shown to have been done by a prior owner.

Frequently Asked Questions

Do I need a certificate of occupancy for a new house in Peoria?
No. Section 111.1 exempts one- and two-family residences from a formal certificate of occupancy; you only need final inspection approval and a utility clearance before moving in.
What triggers a re-inspection fee in Peoria?
Section 109.8 assesses it when the work called for isn't complete, required corrections weren't made, approved plans aren't on site, you don't provide access on the scheduled date, or the work deviates from approved plans without the building official's sign-off.
What happens if I build without a permit in Peoria?
Section 114.4.1 charges an investigation fee in addition to the permit fee, and doubles the permit fee itself, whether or not a permit is eventually issued. The Development and Engineering Department can waive charges only if a prior owner did the unpermitted work.

Sources & Official References

Other rules in Peoria

All Peoria rules

Compare Peoria to another location·View the Arizona building safety overview

Get notified when Building Inspections in Peoria, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Maricopa County handle building inspections.

Mesa, AZ
Some Restrictions
Glendale, AZ
Some Restrictions
Scottsdale, AZ
Some Restrictions
Tempe, AZ
Some Restrictions
Chandler, AZ
Some Restrictions