Scottsdale, AZ Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Special inspections trigger
Complex electrical work
Temporary CO, non-residential
Up to 180 days
Temporary CO, single-family
Up to 90 days
Deposit amount
Greater of permit fees or $2,500
Admin fee on refund
$200
Temp power prerequisite
Pass Building Inspection #024

Summary

Scottsdale's building official can order any inspection needed to verify code compliance beyond the standard required list, plus special inspections for complex electrical work like lightning protection or buried grounding grids. Temporary occupancy before final inspection requires a cash deposit of at least $2,500.

110.3.10 Other inspections. In addition to the inspections specified in Sections 110.3.1 through 110.3.9, the building official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this code and other laws that are enforced by the department of building safety. A complete list of required inspections can be found on the city website and on job cards. 110.3.11 Special inspections. For special inspections, see Chapter 17. The building official may require special inspections for complex electrical installations, such as: a.Lightning protection systems.b.Extensive grounding grid installations.c.An electrical installation that cannot be visually inspected at the time of installation.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 80).

Full Breakdown

Sec. 9 to confirm compliance with the code and other laws enforced by the Department of Building Safety, with the complete required-inspection list posted on the city website and printed on job cards. 11, Special inspections, lets the official require added inspection for complex electrical installations: lightning protection systems, extensive grounding grid installations, and any electrical work that cannot be visually inspected once installed. Sec. 31-9 amends Section 111, Certificate of Occupancy, to allow a temporary certificate before final inspections are complete. For non-single-family buildings, the applicant must diligently finish the remaining work, the temporary certificate expires within 180 days with power de-energized at expiration, and the city and utility bear no liability for resulting damages or delays.

A single-family dwelling can get a temporary certificate for up to 90 days under the same conditions. Every temporary certificate requires a cash deposit equal to all project permit fees or $2,500, whichever is greater, refundable within 30 days of the final certificate of occupancy minus a $200 administrative fee, but forfeited entirely if the building is occupied without a valid certificate. Sec. 31-10 similarly amends Section 112 to allow temporary electrical power for construction and testing once the applicant passes Building Inspection #024, subject to the same deposit structure and a lock-out/tag-out safety plan that must be signed by the permit holder and every worker on site, then posted and kept on the job.

Violations & Fines

Occupying a building before a valid certificate of occupancy issues forfeits the entire temporary-certificate deposit to the city (Sec. 31-9, Section 111.3.1). Using authorized temporary power for anything other than construction or testing lets the building official de-authorize the power immediately and forfeit that deposit as well (Sec. 31-10, Section 112.2.1, 112.2.4). Beyond these deposit forfeitures, an uncorrected inspection failure blocks permit close-out and certificate issuance, and any unresolved code violation is enforceable under the Code's general penalty, Sec. 1-8, a class 1 misdemeanor.

Frequently Asked Questions

Can I move into a Scottsdale house before the final building inspection?
Sec. 31-9 allows a temporary certificate of occupancy for a single-family dwelling for up to 90 days if the building official finds justifiable cause and no substantial hazard, but a cash deposit of at least $2,500 (or the total permit fees, if higher) is required and forfeited if the home is occupied without a valid certificate.
What triggers a special inspection under Scottsdale's building code?
Section 110.3.11, as amended by Sec. 31-8, lets the building official require special inspections for complex electrical installations such as lightning protection systems, extensive grounding grids, or wiring that cannot be visually inspected once it is installed.
Can a contractor get temporary power before the final electrical inspection in Scottsdale?
Yes, under Sec. 31-10. After passing Building Inspection #024, the building official can authorize temporary power for construction or testing only, backed by a deposit of the total permit fees or $2,500, and a signed lock-out/tag-out safety plan posted on site.

Sources & Official References

Other rules in Scottsdale

All Scottsdale rules

Compare Scottsdale to another location·View the Arizona building safety overview

Get notified when Building Inspections in Scottsdale, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Maricopa County handle building inspections.

Mesa, AZ
Some Restrictions
Glendale, AZ
Some Restrictions
Tempe, AZ
Some Restrictions
Peoria, AZ
Some Restrictions
Chandler, AZ
Some Restrictions