Sheboygan, WI Building Safety: Building Inspections (2026)
Key Facts
- Access after written notice
- Within 24 hours of service, 7:00 a.m. to 6:00 p.m.
- Access without notice
- Buildings under construction and public buildings, at all times
- Conditional occupancy cure period
- 45 days, then a reinspection is scheduled
- Occupancy permit trigger
- Commercial building new, altered, converted, or vacant over one year
- Default Chapter 26 forfeiture
- $150.00 to $750.00 plus costs of prosecution
- Reporting duty
- Monthly and annual to Common Council, weekly to local press
Summary
Sheboygan runs building, electrical, plumbing, heating and housing inspections from one building inspection department. Within 24 hours after written notice, the building inspector gets free access between 7:00 a.m. and 6:00 p.m. to any home or premises where permitted work is underway, and access at all times to buildings under construction and public buildings.
A building inspection department is established in the city development department which shall incorporate the functions of building, electrical, plumbing, heating and housing inspections. ... The building inspector, upon written notice stating the reason therefore, shall, within 24 hours after service of such notice, have free and unobstructed access between the hours of 7:00 a.m. and 6:00 p.m., to any part of a private home or premises where work has been performed, or is being performed, pursuant to a permit issued under this article. The inspector shall have free access at all times, without such notification, to any building under construction or any public building for the purpose of determining compliance with the provisions of this article and the applicable state and federal regulations.
Full Breakdown
Section 26-66 establishes a building inspection department inside the city development department and folds the functions of building, electrical, plumbing, heating and housing inspections into it. Under § 26-69 the inspectors carry the powers and duties assigned by the other provisions of the Code, so the stage-by-stage steps for each trade sit in that trade's own article of Chapter 26. The electrical article, for example, requires the person doing the wiring to notify the electrical inspector on completion or before any wiring is hidden from view, and the inspector then has 48 hours to inspect (§ 26-230).
Access is the core inspection power. Under § 26-70 the building inspector, on written notice stating the reason, has free and unobstructed access within 24 hours after service of the notice, between 7:00 a.m. and 6:00 p.m., to any part of a private home or premises where work has been or is being performed under a permit issued under Article II. No notice is needed for a building under construction or any public building: the inspector has free access at all times to determine compliance with the article and the applicable state and federal regulations.
Commercial occupancy has its own inspection step. Section 26-42 makes it unlawful to use a commercial building or premises that is newly erected, altered, converted from its previous occupancy, or vacant for more than one year until the building inspection department issues an occupancy permit. Once an application is received and the occupancy inspection is completed, the department sends an occupancy letter listing all violations, and the permit issues when all violations are corrected. A prospective occupant can request a conditional occupancy permit if the department finds no life-safety violations; the applicant then agrees to correct everything within 45 days, and a reinspection is scheduled after 45 days. No permit is required if the building use stays the same or the building is a legal home occupation.
Record keeping follows the inspections. Under § 26-67 every department employee files a complete inspection report on prescribed forms, the department keeps a record of all inspections and all fees collected, and the manager of planning and inspection services or a designee reports monthly and annually to the Common Council and weekly to the local press on all building activities. A building permit for an existing building, accessory building or accessory structure expires six months from issuance and is void if work does not start within 30 days or stops for more than 60 days (§ 26-44(a)).
Violations & Fines
A violation of Chapter 26 with no specific penalty carries a forfeiture of not less than $150.00 nor more than $750.00, plus the costs of prosecution, and default of payment can mean county jail for up to 90 days; each day is a separate offense (§ 26-1). Under § 26-42, a conditional occupancy holder with violations still open at the 45-day reinspection faces a forfeiture for each day until they are corrected, and the department can revoke any permit of approval for a violation found on inspection or a false statement in the application or plans.
Frequently Asked Questions
Can a Sheboygan building inspector enter my home?
Which Sheboygan office handles electrical, plumbing and heating inspections?
Does a Sheboygan business need an occupancy inspection?
What happens after a Sheboygan occupancy inspection finds violations?
Sources & Official References
Other rules in Sheboygan
Compare Sheboygan to another location·View the Wisconsin building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.