Sherman, TX Building Safety: Building Inspections (2026)
Key Facts
- How to schedule
- Online permit portal, by the contractor
- Results delivered
- Through the contractor's portal account
- Failed inspection
- Correct, then reschedule; reinspection fee applies
- Additional inspection fee
- $30.00 for mechanical, electric, plumbing, solar
- Utility meters
- No permanent meter until construction is approved
- Permit lapse
- Six months without an inspection
Summary
In the City of Sherman, Texas, contractors schedule every required building inspection through the city's online permit portal and read the results there. A failed inspection must be corrected and rescheduled, with a non-refundable reinspection fee. Proceeding with or concealing work that has not passed inspection is unlawful.
(a) Inspection scheduling.It is the responsibility of all contractors to use the online permit portal to schedule inspections. ... (c) Inspection notification.Notification of the results of a building inspection will be provided through the online permit portal. All contractors must use their account to check the status of their inspection. (d) Failed inspections.If the inspection has failed, the work must be corrected and then rescheduled for inspection. Reinspection fees are established as set forth in the city's fee schedule (Appendix C of this code), as approved by city council and as may be amended from time-to-time. The prescribed fee is not refundable. (e) Proceeding without passed inspection.It shall be unlawful for any person to proceed with any work requiring an inspection or conceal any work unless the work has been inspected and passed. It shall be unlawful to proceed with or conceal any work that has failed inspection.
Full Breakdown
Section 3.01.005 of the Sherman Code of Ordinances puts the scheduling burden on the contractor: inspections are requested through the city's online permit portal, results are posted there, and contractors must check their account for status. A city building inspector records all findings digitally in the city's system at the time of the inspection. A failed inspection means the work is corrected and then rescheduled, and reinspection fees come from the Appendix C fee schedule and are not refundable. Appendix C prices single-family mechanical, electric and plumbing permits at $75.00 and $30.00 for each additional inspection, and lists the same figures for solar and irrigation permits.
Sequence matters. It is unlawful to proceed with or conceal any work requiring inspection unless the work has been inspected and passed, and unlawful to proceed with or conceal work that failed. Subsection (f) bars gas, light, water and electric utilities from permanently installing a meter until construction has been approved. Temporary construction electrical service must be inspected and approved by a building inspector after installation before it connects to the distribution system (§ 3.03.003(4)(B)).
Inspections also keep a permit alive. Under § 3.01.002, a permit expires if no inspection occurs within six months, and extensions run six months at a time to a two year ceiling. Several amendments add engineer sign-off on top of the city's own inspections: foundation repairs need a letter bearing the engineer's stamp (§ 3.03.001(4)), an engineer of record inspects any retaining wall four feet or greater (§ 3.03.002(6)), and the thermal envelope of every residential and non-residential building must be inspected and tested by a third-party inspector (§ 3.03.007(2)). Construction sites must also meet § 3.01.006, which requires a portable water closet and temporary perimeter fencing at least 4 feet in height.
Violations & Fines
Proceeding with or concealing work that is uninspected or failed is unlawful under § 3.01.005(e), and § 3.01.008 makes article violations punishable under § 1.01.009: a fine up to $500.00, or up to $2,000.00 where the rule governs fire safety or zoning, with each day a separate offense. Two convictions in twelve months, including failing to request required inspections, can cost a contractor its city registration.
Frequently Asked Questions
How do I request a building inspection in Sherman?
What happens if my inspection fails?
Can I cover up framing or wiring before the inspector arrives?
When can the power company set a permanent meter?
Sources & Official References
Other rules in Sherman
Texas rules heatmap·Compare Sherman to another location·View the Texas building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.