Key Facts
- Standard cap
- 50% ISR in SR-1AA, SR-1A, SR-1, MR-2, MR-3
- PD cap
- 60% impervious surface for planned developments
- Formula
- Impervious sq ft divided by lot sq ft
- Example given
- 4,000 sq ft on 10,000 sq ft lot = 40%
- Remedy if exceeded
- Remove, swap, or apply for a variance
Summary
In the City of Sanford, Florida, the Land Development Regulations cap impervious surface ratio (ISR) at 50 percent of lot area in the SR-1AA, SR-1A, SR-1, MR-2 and MR-3 zoning districts, and at 60 percent for planned development (PD) projects, calculated as impervious area in square feet divided by total lot area.
B.Calculating the impervious surface on your property. Impervious surface ratio (ISR) calculations and other information shall be provided with all applications. Calculations for the ISR shall be determined as follows:1.Impervious Area in sq. ft. / Entire Lot Area in sq. ft. = ISR ... a.No more than 50% entire lot ISR is allowed within the following zoning districts: SR-1AA, SR-1A, SR-1, MR-2, MR-3.b.No more than 60% impervious for PD zoning as set forth in the controlling development order.
Full Breakdown
"Impervious surface" is defined as any hard surface or structure, such as a roof, driveway, sidewalk, patio or pool, made of concrete, pavers, asphalt or similar material that keeps rainwater from soaking into the ground; the city ties the cap to flooding, drainage and water-quality concerns from polluted runoff. Every application must include an ISR calculation, using impervious square footage divided by entire lot square footage, and the regulations give a worked example of 4,000 square feet of impervious area on a 10,000-square-foot lot equaling a 40 percent ISR.
If a proposed project would push a lot above its 50 or 60 percent cap, the property owner has two options under the Schedule: remove an equal amount of existing impervious surface, such as excess patio or pool decking, or swap one impervious feature for another of the same size, such as removing an old shed to add a new patio. A property owner may also apply for a variance to exceed the cap, but the application must include a plan addressing the increased stormwater runoff the project would cause.
Any pervious pavement or non-compacted surface material only counts as pervious if it is continually kept free of clay or fine particles that would otherwise block water from percolating through it, and projects remain subject to other city, state and agency standards such as setbacks and wetland buffers.
Violations & Fines
Adding any building or improvement that pushes a lot's impervious surface above its district's 50 or 60 percent cap is barred outright unless the owner first removes or swaps out an equivalent amount of existing impervious area, or obtains a variance supported by a runoff-management plan; the Administrative Official implements this Schedule through development orders and can deny a development order for a project that exceeds the calculated ISR.
Frequently Asked Questions
What percentage of my Sanford lot can be paved or covered?
How is impervious surface ratio calculated in Sanford?
What happens if a Sanford project exceeds the impervious surface cap?
Sources & Official References
Other rules in Sanford
Florida rules heatmap·Compare Sanford to another location·View the Florida building setbacks & zoning overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.