Terrebonne Parish, LA Building Setbacks & Zoning: Lot Coverage Limits (2026)
Key Facts
- Governing section
- Terrebonne Parish Code § 6-23
- Coverage trigger
- Over 70% impervious or 10,000 sq ft
- Applies to
- Commercial and industrial development
- Reviewing agency
- TPCG Department of Public Works
- Standard applied
- Parish Storm Drainage Design Manual
- Occupancy hold
- Engineer certification required before occupancy
Summary
Commercial and industrial developments in Terrebonne Parish that pave, build or otherwise cover more than 70 percent of a lot, or more than 10,000 square feet of it, cannot get a building permit without extra drainage review. Parish Code § 6-23 requires those projects to submit plats and calculations to the Department of Public Works and follow the parish's Storm Drainage Design Manual.
(1)All commercial or industrial development:a.Which will result in making impervious to rainfall (concrete, blacktop and/or structures) more than seventy (70) percent of a lot or more than ten thousand (10,000) square feet of a lot including structures; and ... c.In all cases which will result in making impervious to rainfall more than seventy (70) percent of a lot, the plans shall be submitted to the TPCG Department of Public Works for approval. The development of the property shall conform to the requirements of the TPCG's Storm Drainage Design Manual, as amended.
Full Breakdown
Terrebonne Parish Code § 6-23 does not set a hard ceiling on how much of a residential lot can be covered; instead it creates a mandatory engineering review for commercial and industrial projects once the site crosses an impervious-surface threshold. Before the parish will approve a building permit, an applicant must submit adequate plats, plans, calculations and approvals showing compliance. Two triggers apply: making more than 70 percent of the lot impervious to rainfall through concrete, blacktop or structures, or covering more than 10,000 square feet of the lot with impervious surface, whichever standard is met first.
Any project that was not already engineering-approved by the parish planning commission before Ordinance No. 5293 took effect on August 25, 1994, and that will push a lot's imperviousness above 70 percent, must have its plans submitted to the Terrebonne Parish Consolidated Government Department of Public Works, and the development must conform to the requirements of the parish's Storm Drainage Design Manual as amended. The section also folds in road-construction standards: any improvement the developer intends to dedicate to the parish must be built to the latest LaDOTD Standard Specifications for Roads and Bridges and comply with LaDOTD standard plans, with exceptions allowed only by written approval of the director of public works.
1 of Appendix B of the parish code. The planning and zoning director can condition a permit's issuance on the timing of drainage mitigation work, and before a certificate of occupancy issues, the project engineer must certify to the parish engineering department that drainage improvements were built to the approved plans and specifications.
Violations & Fines
A commercial or industrial project that exceeds the 70 percent, or 10,000-square-foot, impervious threshold without the required Department of Public Works plan approval cannot obtain a building permit under § 6-23, and the planning and zoning director can withhold or condition permit issuance on completing drainage mitigation work. A certificate of occupancy will not issue until the project engineer certifies to the parish engineering department that the drainage improvements match the approved plans.
Frequently Asked Questions
Is there a maximum lot coverage limit in Terrebonne Parish?
Does this impervious coverage rule apply to residential lots?
What has to be submitted before a large commercial project is approved?
Sources & Official References
Other rules in Terrebonne Parish
Compare Terrebonne Parish to another location·View the Louisiana building setbacks & zoning overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.