Data Centers & Crypto Mining in Kyle, TX (2026)
2 verified data centers & crypto mining rules for Kyle, Texas, sourced directly from the municipal code and official government pages.
Verified from official government sources
Data Center Zoning & Siting
In the City of Kyle, data centers are a permitted use only inside the Plum Creek Planned Unit Development's "EMP" employment district, not automatically citywide. Chapter 53A of the Kyle City Code lists "Data centers" among the district's by-right uses and applies standard EMP site development rules: a 5,750-square-foot minimum lot, a 75-foot height cap and a 1.5 floor area ratio.
Kyle Plum Creek EMP District Data Centers
Some RestrictionsKyle City Code Ch. 53A, Art. II, Sec. 9(B)(17), (C)(3)(a),(b),(c),(d),(g)
(17) Data centers. (C) Site development regulations.A letter of approval from the architectural review committee shall be submitted with an application for a site plan. ... (3) The following regulations shall be applicable to the "EMP" employment district: (a) Minimum lot size: 5,750 square feet. (b) Minimum lot width: 50 feet. (c) Minimum lot depth: 100 feet. (d) Maximum height: No building or...
Data Center Noise Limits
Kyle's Plum Creek Planned Unit Development sets a district-wide noise ceiling for its "EMP" employment district, the zone where data centers are a permitted use: no more than 70 dBA at the property line next to commercial land, tightening to 65 dBA where the property line adjoins R-1, R-2 or R-3 residential zoning.
Kyle Plum Creek EMP District Noise Cap
Some RestrictionsKyle City Code Ch. 53A, Art. II, Sec. 9(C)(3)(e)
(e) Maximum sound levels to be 70 dBA measured at the property line if adjacent to commercial and 65 dBA measured at the property line if adjacent to R-1, R-2, or R-3 property.