Stormwater Management
Murray requires a city-issued permit before any land disturbance within the city limits, issued once a sedimentation and erosion control plan is approved. Section 156.095 covers sites of one acre or more, requires inspections every seven days, and § 156.999(C) sets a civil penalty of $250 per violation per day.
Murray Stormwater and Erosion Control: Permit for Land Disturbance
Some RestrictionsMurray Code of Ordinances § 156.095
(A) Permit required. Prior to any person engaging in a land disturbance activity within the corporate boundaries of the city, they shall possess a city-issued permit for the land disturbance activity. A permit will be issued by the city once a sedimentation and erosion control plan has been submitted and approved. ... (1) Land disturbing activities including development and re-development activ...
Erosion Control
In Murray, anyone starting a land disturbance activity needs a city-issued permit, which the city issues once a sedimentation and erosion control plan is submitted and approved under Murray Code of Ordinances § 155.35. Sites of one acre or more fall under NPDES coverage, and no disturbed area may sit bare longer than fourteen days.
Murray KY Erosion and Sediment Control Permit
Some RestrictionsMurray Code of Ordinances § 155.35
(A) Permit required. Prior to any person engaging in a land disturbance activity within the corporate boundaries of the city, they shall possess a city-issued permit for the land disturbance activity. A permit will be issued by the city once a sedimentation and erosion control plan has been submitted and approved. ... (1) Land disturbing activities including development and re-development activ...
Flood Zones
In Murray, no construction or other development may begin inside a FEMA special flood hazard area until the owner holds a development permit issued on forms furnished by the Floodplain Administrator under Murray Code of Ordinances § 152.25. The mapped areas come from the Flood Insurance Study for the City of Murray dated September 29, 2010.
Murray KY Flood Zone Development Permit Rules
Some RestrictionsMurray Code of Ordinances § 152.25
(A) (1) A Development Permit shall be required in conformance with the provision of this chapter prior to the commencement of any development activities in the special flood hazard areas (SFHA). See division (B) for instructions and explanation. (2) Application for a development permit shall be made on forms furnished by the Floodplain Administrator. (B) A development permit shall be obtained b...
Flood Elevation Requirements
In Murray, new residential construction and substantial improvements in a special flood hazard area with base flood elevation data must have the lowest floor, basement, mechanical equipment and ductwork elevated no lower than one foot above the base flood elevation, under Murray Code of Ordinances § 152.41(A). An engineer or surveyor certifies the finished elevation.
Murray KY Base Flood Elevation and Freeboard Rules
Some RestrictionsMurray Code of Ordinances § 152.41
In all special flood hazard areas where base flood elevation data have been provided, as set forth in § 152.08, the following provisions are required: (A) Residential construction . (1) New construction or substantial improvement of any residential structure (or manufactured home) shall have the lowest floor, including basement, mechanical equipment, and ductwork elevated no lower than one foot...