Generator noise control
Enclosed building, adequate ventilation
Residential buffer
500 feet minimum
Allowed districts
MU-ED, GID, HID only
Entitlement required
Use permit under Section 6-308
Added by
Ordinance O2025.23, effective 7-1-2025

Summary

Tempe's Zoning and Development Code requires data center generators to sit inside an enclosed, ventilated building specifically to cut noise reaching neighbors, and keeps data center buildings themselves at least 500 feet from any residential use or residential district under Section 3-429(B). The rule applies only in the MU-ED, GID and HID districts where data centers are allowed with a use permit.

A.Purpose and Applicability. the purpose of this section is to allow data centers in areas that limit the impact of identified innovation hubs and rail corridors where job employment growth and commerce are desired... design standards adopted to mitigate noise levels. data centers are allowed in the mu-ed. gid and hid zoning districts only, subject to approval of a use permit, pursuant to section 6-308.B.Location Requirements.1.Data center buildings shall not be located within 500 feet of the property line of a site containing a residential use or a residential district.2.Generators for data centers shall be located within an enclosed building with necessary ventilation to reduce impacts on noise to surrounding area.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Code: Supplement 33 Update 4 | Zoning and Development Code: Supplement 11 Update 2).

Full Breakdown

Section 3-429 was added to the Zoning and Development Code by Ordinance No. 23, effective July 1, 2025, to steer data centers into the city's innovation hubs and rail corridors while limiting neighborhood impact. Data centers are allowed only in the MU-ED, GID and HID zoning districts, and only after approval of a use permit under Section 6-308. Section 3-429(B)(1) sets a flat 500-foot buffer between any data center building and the property line of a site with a residential use or residential zoning district.

Section 3-429(B)(2) targets the loudest equipment specifically: generators serving a data center must sit inside an enclosed building with ventilation adequate to reduce the noise impact reaching the surrounding area, rather than running in open yards or on exposed pads. Section 3-429(A) folds these location and design rules into a broader purpose clause calling for design standards adopted to mitigate noise levels alongside energy and water consumption controls. Beyond noise, Section 3-429(C) requires an economic impact study reviewed by the Economic Development Director for any proposed innovation-hub or rail-corridor site, and any data center meeting the code's definition of an extreme-water-use facility must also submit a water use plan to the Public Works Department under Tempe City Code Section 33-142 before a use permit can be granted.

Violations & Fines

A data center that runs generators in the open, without an enclosed and ventilated housing, or that locates within 500 feet of a residential property line, violates Section 3-429(B) and Section 1-201 of the Code. The city can issue a civil citation carrying a $100 to $1,000 fine per day of noncompliance or prosecute it as a class 1 misdemeanor with up to a $2,500 fine and six months in jail, and a noncompliant use permit can be revoked.

Frequently Asked Questions

Does Tempe set a decibel limit for data center noise?
No decibel number appears in Section 3-429. Instead the code requires generators to sit inside an enclosed building with ventilation sufficient to reduce noise reaching the surrounding area, and keeps data center buildings 500 feet from any residential property line.
Where can a data center locate in Tempe?
Only in the MU-ED, GID and HID zoning districts, and only with an approved use permit under Section 6-308. The Economic Development Director also reviews an economic impact study before the city approves a site in an innovation hub or rail corridor.
Can a data center run generators outdoors in Tempe?
No. Section 3-429(B)(2) requires generators serving a data center to be located within an enclosed building with necessary ventilation, specifically to reduce noise impacts on the surrounding area, so open-air generator yards are not code compliant.

Sources & Official References

Other rules in Tempe

All Tempe rules

Compare Tempe to another location·View the Arizona data centers & crypto mining overview

Get notified when Data Center Noise Limits in Tempe, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Noise Limits in Nearby Cities

How other cities in Maricopa County handle data center noise limits.

Mesa, AZ
Some Restrictions
Phoenix, AZ
Some Restrictions
Goodyear, AZ
Some Restrictions
Chandler, AZ
Heavy Restrictions