Tempe, AZ Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Allowed districts
- MU-Ed, GID, HID only
- Approval required
- Use permit under Section 6-308
- Residential buffer
- 500 feet minimum
- Generators
- Must be fully enclosed
- Extra filing
- Economic impact study required
- Adopted
- Ord. No. O2025.23, 7-1-2025
Summary
Tempe confines data centers to the MU-Ed, General Industrial and Heavy Industrial zoning districts, and only with an approved use permit under the Zoning and Development Code. Buildings must sit at least 500 feet from any residential use, and generators must be fully enclosed to control noise reaching neighboring properties.
A.Purpose and Applicability. the purpose of this section is to allow data centers in areas that limit the impact of identified innovation hubs and rail corridors where job employment growth and commerce are desired. sustainability measures are addressed through appropriate land planning, energy and water consumption are mitigated through infrastructure evaluation, and design standards adopted to mitigate noise levels. data centers are allowed in the mu-ed. gid and hid zoning districts only, subject to approval of a use permit, pursuant to section 6-308.B.Location Requirements.1.Data center buildings shall not be located within 500 feet of the property line of a site containing a residential use or a residential district.2.Generators for data centers shall be located within an enclosed building with necessary ventilation to reduce impacts on noise to surrounding area.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Code: Supplement 33 Update 4 | Zoning and Development Code: Supplement 11 Update 2).
Full Breakdown
Section 3-429 of Tempe's Zoning and Development Code limits data centers to three zoning districts: the Mixed-Use Educational (MU-Ed) district on Arizona State University land, and the General Industrial (GID) and Heavy Industrial (HID) districts elsewhere. The stated purpose is to steer data centers toward the city's designated innovation hubs and rail corridors, where job growth and commerce are prioritized, while managing impacts through land planning, review of energy and water consumption, and noise-mitigation design standards. Every data center use requires a use permit under Section 6-308 regardless of district.
The location standard in Section 3-429(B) bars a data center building from sitting within 500 feet of the property line of any residential use or residential zoning district. Backup generators serving the facility must be housed inside an enclosed building with ventilation engineered to cut the noise that reaches surrounding parcels; an exposed pad-mounted generator does not meet this standard.
Beyond the general use-permit approval criteria in Section 6-308(E), Section 3-429(C) requires the applicant to submit an economic impact study for the Economic Development Director, or a designee, evaluating whether locating the data center in an innovation hub or rail corridor would displace higher-employment uses. A facility that qualifies as an "extreme-water use" under the code must also file a water use plan with the Public Works Department under Tempe City Code Section 33-142. The city adopted this section by Ordinance No. O2025.23 on July 1, 2025.
Violations & Fines
Operating a data center without an approved use permit, siting a building inside the 500-foot residential buffer, or running generators outside an enclosed, ventilated structure violates Section 3-429. Community Development can withhold or revoke the use permit, require the operator to relocate or enclose non-conforming equipment, and pursue a civil sanction under Section 1-201 until the site is brought into compliance.
Frequently Asked Questions
Where can a data center legally locate in Tempe?
How close can a data center be to a house?
Do the backup generators need special enclosures?
What extra paperwork does a data center project need?
Sources & Official References
Other rules in Tempe
Compare Tempe to another location·View the Arizona data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Data Center Zoning & Siting in Nearby Cities
How other cities in Maricopa County handle data center zoning & siting.