Key Facts

Districts
GI (M-2) and HI only
Approval
Council PAD Overlay required
Residential Separation
400 feet
Max Height
60 feet
Code
Sec. 11-31-36 (Ord. 5957)

Summary

Since Ordinance No. 5957 (adopted July 8, 2025), a standalone data center is allowed only in General Industrial (GI) or Heavy Industrial (HI) zoning, and only when City Council specifically authorizes it through a Planned Area Development (PAD) Overlay District.

May be permitted only if specifically authorized by City Council at the time of approval of a Planned Area Development Overlay (PAD) District.

Source: Mesa Zoning Ordinance (Title 11) & Mesa City Code Ch. 6-12View official code

Full Breakdown

Mesa previously reviewed data centers as "Indoor Warehousing and Storage." Ordinance No. 5957 replaced that interpretation, adding Section 11-31-36. A principal-use data center is not allowed by right; it is designated "SE" in GI (M-2) and HI districts and requires a Council-approved PAD Overlay. Light Industrial (LI/M-1) and Planned Employment Park (PEP) do not permit principal data centers. Section 11-31-36 imposes a 400-foot separation from residential, a 60-foot maximum height, all-sided architecture, glazing, and screening of mechanical equipment and ground-mounted substation gear. Applications require an operational plan, good-neighbor policy, water/thermal-management report, wastewater report, energy-service report, and an initial sound study. Data centers approved before the effective date are legal conforming uses; Eastmark is exempt from Section 11-31-36.

Violations & Fines

Civil sanctions run $150-$1,500 per citation, rising to $250-$2,500 (second offense within 24 months) and $500-$2,500 (third within 36 months). Each day is a separate offense; habitual offenders face a class 1 misdemeanor.

Frequently Asked Questions

Can a data center be built by right in Mesa?
No. A standalone data center needs City Council authorization through a Planned Area Development Overlay combined with General or Heavy Industrial zoning, plus compliance with Section 11-31-36 standards.
How far must a data center sit from homes?
Section 11-31-36 requires a 400-foot separation from residential uses, with a 60-foot building height cap, all-sided architecture, and screening of mechanical and substation equipment.
What about small server rooms?
A data center serving only the on-site owner, not leased to third parties, under 10% of the building, and not stand-alone is an accessory use allowed in commercial and employment districts without Section 11-31-36 review.

Sources & Official References

Other rules in Mesa

All Mesa rules

Compare Mesa to another location·View the Arizona data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Mesa, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Maricopa County handle data center zoning & siting.

Peoria, AZ
Some Restrictions
Phoenix, AZ
Significant Restrictions
Tempe, AZ
Significant Restrictions
Goodyear, AZ
Significant Restrictions
Glendale, AZ
Significant Restrictions
Chandler, AZ
Heavy Restrictions