Goodyear, AZ Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permitted as principal use
Industrial Districts only
Accessory-use exemption cap
10% of gross floor area
Residential/noise-sensitive setback
300 feet
Pre-permit documentation
Electric + water usage plans
Reviewed under
Section 6.3 site plan process

Summary

Goodyear allows data centers as a principal use only in Industrial Districts, subject to site plan review, utility and water documentation, and a 300-foot setback from residential zoning or noise-sensitive uses for the building and its support equipment.

3.11.16. Data Centers A. Applicability. 1. Principal Use. Data centers are permitted to operate as a principal use in Industrial Districts subject to the requirements of this section. 2. Accessory Use. A Data Center that meets all of the criteria below may be considered an accessory use and is not subject to the requirements of this Section. a. The Data Center exclusively serves the enterprise functions of the on-site property owner or tenant. b. The Data Center does not lease data storage or processing services to third parties. c. The Data Center occupies no more than 10% of the total gross floor area of all buildings on the site. ... C. Development Standards 1. Setbacks. ... a. A minimum setback of three hundred (300) feet shall be provided from any property that is zoned for residential use or from any property containing an existing residential dwelling unit or other existing noise-sensitive use, as determined by the Zoning Administrator, or his or her designee.

Full Breakdown

16(A)(1) permits data centers to operate as a principal use in Industrial Districts, subject to the full requirements of the section. A narrower carve-out in (A)(2) lets a Data Center be treated as an accessory use, exempt from the section, if it exclusively serves the enterprise functions of the on-site property owner or tenant, does not lease data storage or processing services to third parties, and occupies no more than 10% of the total gross floor area of all buildings on the site. 16(B) requires a narrative explaining compliance with each requirement, an operational plan demonstrating zoning, building and fire safety compliance, Electric Service Documentation from the intended utility provider affirming sufficient power exists (which can be waived or amended by the Zoning Administrator for multi-phased projects), and Water Usage Documentation identifying the intended water source and an estimate of annual water consumption.

Development Standards in (C)(1)(a) require a minimum 300-foot setback for the data center building itself, plus its cooling, ventilating, power generator, backup generator, and other power supply equipment, from any property zoned for residential use or containing an existing residential dwelling unit or other existing noise-sensitive use, as determined by the Zoning Administrator. 23, and landscaping replacement duties tied to powerline work serving the facility.

Violations & Fines

A data center that cannot produce the required Electric Service and Water Usage Documentation, or the narrative and operational plan Section 3.11.16(B) requires, does not get its site plan or building permit approved. The Zoning Administrator can waive or amend the electric documentation for multi-phased projects, but the 300-foot residential/noise-sensitive setback in (C)(1)(a) is not listed among the standards subject to that discretion.

Frequently Asked Questions

Where can a data center legally locate in Goodyear?
Section 3.11.16(A)(1) allows data centers as a principal use only in Industrial Districts, subject to the section's site plan, documentation and development standards; a small on-site data room can skip those requirements only if it meets the accessory-use test in (A)(2).
How far must a data center building sit from homes?
At least 300 feet. Section 3.11.16(C)(1)(a) requires that setback from any property zoned residential or containing an existing residential dwelling or other noise-sensitive use, for the data center building itself and for its cooling, ventilating, generator and power-supply equipment.
What paperwork does a data center need before a permit?
Section 3.11.16(B) requires a narrative showing compliance with the section, an operational plan addressing zoning, building and fire-safety compliance, documentation from the electric utility confirming sufficient power exists, and a water-source estimate of annual consumption.
Does every on-site server room count as a regulated data center?
No. Section 3.11.16(A)(2) exempts a Data Center from the section entirely if it exclusively serves the property owner's or tenant's own operations, does not lease capacity to third parties, and occupies no more than 10% of the site's total gross floor area.

Sources & Official References

Other rules in Goodyear

All Goodyear rules

Compare Goodyear to another location·View the Arizona data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Goodyear, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Maricopa County handle data center zoning & siting.

Mesa, AZ
Some Restrictions
Peoria, AZ
Some Restrictions
Phoenix, AZ
Significant Restrictions
Tempe, AZ
Significant Restrictions
Glendale, AZ
Significant Restrictions
Chandler, AZ
Heavy Restrictions