Glendale, AZ Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

C-1 / PR districts
Prohibited
C-2 / C-3 districts
Conditional Use Permit required
B-P / M-1 / M-2 districts
Conditional Use Permit required
Parking
Parking Justification Study required (§ 35.4.005(E))
Definition
§ 35.8.003

Summary

Glendale treats a data center as a conditional use almost everywhere it's allowed: Table 2.500-1 permits it only with a Conditional Use Permit in the C-2 and C-3 commercial districts, and Table 2.700-1 requires the same CUP in all three Business/Industrial districts (B-P, M-1, M-2).

Data Center: A facility whose primary service is data processing and is used to house computer systems and associated components, such as telecommunications and storage systems, including but not limited to web hosting organizations and internet service organizations. A server farm, telecom hotel, carrier hotel, telco hotel, telehouse co-location center, or any other term applicable to facilities which are used for these specified purposes shall be deemed to be a data center. [...] Table 2.500-1: C-1 C-2 C-3 PR. Data Center X C C X. [...] Table 2.700-1: Table of Allowed Uses for Business/Industrial Districts. B-P M-1 M-2. Data Center C C C

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 115).

Full Breakdown

003 defines a 'Data Center' as a facility whose primary service is data processing, used to house computer systems and associated components such as telecommunications and storage systems, including web hosting and internet service organizations, and the definition sweeps in a server farm, telecom hotel, carrier hotel, telco hotel, or telehouse co-location center under the same term. 502), a data center is prohibited outright (X) in the C-1 Limited Commercial and PR Pedestrian Retail districts, but allowed with a Conditional Use Permit (C) in C-2 General Commercial and C-3 Heavy Commercial.

702), the Business/Industrial districts treat it the same way across the board: B-P (Business Park), M-1 (Light Industrial), and M-2 (Heavy Industrial) all require a Conditional Use Permit (C) rather than allowing it by right. 208's conditional use review process. 000-2.

Violations & Fines

Building or operating a data center anywhere in Glendale without an approved Conditional Use Permit under Section 35.6.208, or in the C-1 or PR districts where it's flatly prohibited, is a Unified Development Code violation. Absent a use-specific fine in Title 35, Section 1-7's general penalty controls: a Class 1 misdemeanor with each day of the violation a separate offense, plus the City's option to pursue it as a civil code infraction in City Court.

Frequently Asked Questions

Can a data center be built by right anywhere in Glendale?
No, every zoning district that allows one, C-2, C-3, B-P, M-1, and M-2, requires a Conditional Use Permit under Section 35.6.208; it's flatly prohibited in the C-1 and Pedestrian Retail (PR) districts.
What zoning districts allow a data center in Glendale?
Table 2.500-1 allows it with a CUP in the C-2 and C-3 commercial districts, and Table 2.700-1 allows it with a CUP in all three Business/Industrial districts, B-P, M-1, and M-2.
Does a data center have a fixed parking requirement in Glendale?
No, Section 35.4.005(E) requires a Parking Justification Study instead of a standard ratio, covering projected demand under the ITE Parking Generation Manual, nearby available parking, and access to transit.

Sources & Official References

Other rules in Glendale

All Glendale rules

Compare Glendale to another location·View the Arizona data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Glendale, AZ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Maricopa County handle data center zoning & siting.

Mesa, AZ
Some Restrictions
Peoria, AZ
Some Restrictions
Phoenix, AZ
Significant Restrictions
Tempe, AZ
Significant Restrictions
Goodyear, AZ
Significant Restrictions
Chandler, AZ
Heavy Restrictions