Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Dedicated ordinance
None
Zones
M-1, M-2 manufacturing
Unlisted uses
Deemed Not Permitted
CUP trigger
Public utility classification
Discretionary review
CEQA + Planning Commission

Summary

The City of Downey has no data-center ordinance and no "data center" use category. Data centers site in the M-1 and M-2 manufacturing zones, classified into the nearest Table 9.3.9 use: permitted by right as office, R&D, or warehouse, or needing a Conditional Use Permit as a public utility.

Table 9.3.9 identifies the uses permitted in each Manufacturing Zone. If a use is not specifically listed on the table then said use shall be deemed as Not Permitted.

Source: Downey Municipal Code, Article IX Zoning (Manufacturing Zones) & Chapter 6 NoiseView official code

Full Breakdown

Downey's Zoning Code (Municipal Code Article IX) does not name "data center" as a use, and its use tables state that any use not specifically listed is deemed Not Permitted. So the Planning Division must classify a data center into the closest listed use in Table 9.3.9 for the M-1 (light manufacturing) and M-2 (general manufacturing) zones. Read as business offices, research and development, or a warehouse, a server building is Permitted (P) by right with a ministerial building permit. Read as "Public utilities," it needs a Conditional Use Permit under Section 9824 - a discretionary permit triggering CEQA review and a Planning Commission hearing. Downey has adopted no moratorium.

Violations & Fines

Building or operating a data center outside the M-1 or M-2 zones, or without a required Conditional Use Permit, is a Zoning Code violation enforced by Downey Code Enforcement through stop-work orders, citations, and abatement.

Frequently Asked Questions

Where can data centers be built in the City of Downey?
In the M-1 and M-2 manufacturing zones under Municipal Code Article IX. Downey has no data-center use category, so the Planning Division classifies each project into the closest listed use in Table 9.3.9.
Does Downey require a special permit for a data center?
Sometimes. Read as an office, R&D, or warehouse use, it is permitted by right. Read as a public utility, it needs a Conditional Use Permit under Section 9824, with CEQA review.
Does Downey have a data-center ordinance, and who do I ask for one?
No. Downey has adopted no data-center ordinance or moratorium. Ask the City's Planning Division or Planning Commission to adopt tailored standards at downeyca.org/our-city/departments/community-development/planning.

Sources & Official References

Other rules in Downey

All Downey rules

California rules heatmap·Compare Downey to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Downey, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Los Angeles County handle data center zoning & siting.

Long Beach, CA
Light Restrictions
Los Angeles, CA
Some Restrictions
El Monte, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Torrance, CA
Some Restrictions
Palmdale, CA
Some Restrictions
Lakewood, CA
Some Restrictions
Norwalk, CA
Some Restrictions