Fresno, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Few Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Dedicated ordinance
None
Districts
IL, IH industrial
Permit level
By-right (P)
Use classification
Communication facility / industrial
Code
Development Code Table 15-1302

Summary

The City of Fresno has no data-center ordinance and no "data center" use category. Data centers site in the IL Light Industrial and IH Heavy Industrial districts, permitted by right as a Communication Facility or industrial use under Development Code Table 15-1302.

The IL district is intended to provide areas, as identified by the General Plan, for a diverse range of light industrial uses, including limited manufacturing and processing, research and development, fabrication, utility equipment and service yards, wholesaling, warehousing, and distribution activities.

Source: City of Fresno Citywide Development Code (Ch. 15) & Noise Ordinance (Ch. 10, Art. 1)View official code

Full Breakdown

Fresno is a charter city governed by its own Citywide Development Code (Municipal Code Chapter 15), not the County ordinance. The code names no "data center" use. Under Section 15-1302.C the Director assigns an undefined use to the substantially-similar classification. A server building fits "Communication Facilities - Facilities within Buildings" (telephone switching centers), permitted by right in the IL Light Industrial and IH Heavy Industrial districts, or an industrial use such as Limited or General Industrial, also permitted by right in both. No Conditional Use Permit is required for those classifications. Discretionary building approvals trigger CEQA review. Fresno has adopted no data-center ordinance and no moratorium.

Violations & Fines

Building or operating a data center outside an industrial district, or without a required permit, violates the Citywide Development Code and is enforced by Planning and Code Enforcement through stop-work orders and abatement.

Frequently Asked Questions

Where can data centers be built in the City of Fresno?
In the IL Light Industrial and IH Heavy Industrial districts, permitted by right. Fresno's Citywide Development Code has no data-center use, so the Planning Director classifies each facility as a communication or industrial use under Table 15-1302.
Does the City of Fresno require a special permit for a data center?
No. As a communication facility or industrial use, a data center is permitted by right in the IL and IH districts. No Conditional Use Permit is needed, though discretionary building approvals trigger CEQA review.
Has the City of Fresno banned or paused data centers?
No. Fresno has adopted no moratorium and no data-center ordinance. To request tailored standards, contact the City's Planning and Development Department or Planning Commission at fresno.gov/planning.

Sources & Official References

Other rules in Fresno

All Fresno rules

California rules heatmap·Compare Fresno to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Fresno, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Fresno County handle data center zoning & siting.

Clovis, CA
Light Restrictions