Hayward, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Dedicated ordinance
Yes, adopted April 2026
Permit
Major Conditional Use Permit
Decision body
City Council public hearing
Zones
IL, IP, IG industrial
Review
CEQA + benefits plan

Summary

The City of Hayward regulates data centers directly. An April 2026 code amendment created a specific data-center use category and requires every new data center to obtain a Major Conditional Use Permit, approved by the City Council at a public hearing, with CEQA review.

the Hayward City Council amended the Hayward Municipal Code in April of 2026 to create a specific data center category and require that any new data center application be subject to Major Conditional Use Permit approval, which requires a public hearing with the City Council.

Source: City of Hayward Zoning Ordinance (HMC Ch. 10) & Data Center Development RequirementsView official code

Full Breakdown

Data centers locate in Hayward's Industrial District subdistricts - Light Industrial (IL), Industrial Park (IP), and General Industrial (IG) - under Zoning Ordinance Section 10-1.1600. Until April 2026 the code had no data-center use, so projects were processed as "office" use and approved administratively; four facilities were built that way, including Amazon's SF09 and SF011 and STACK's 76.6 MW campus. In April 2026 the City Council amended the Municipal Code to create a specific data-center category. Every new data center now needs a Major Conditional Use Permit decided by the City Council at a public hearing, CEQA review, a Sustainability Plan, and a Community Benefits Plan. Owners within 300 feet receive mailed notice.

Violations & Fines

Building or operating a data center without the required Major Conditional Use Permit, or outside an Industrial subdistrict, is a Zoning Ordinance violation enforced by Development Services through stop-work orders, penalties, and permit revocation.

Frequently Asked Questions

Where can data centers be built in Hayward?
In the Industrial District subdistricts - Light Industrial, Industrial Park, and General Industrial - under Zoning Ordinance Section 10-1.1600. As of April 2026, each new data center also needs a Major Conditional Use Permit from the City Council.
Does Hayward require a special permit for a data center?
Yes. Since April 2026 every new data center needs a Major Conditional Use Permit approved by the City Council at a public hearing, plus CEQA review, a Sustainability Plan, and a Community Benefits Plan.
How can I weigh in on a Hayward data center proposal?
Each application gets a City Council public hearing, and owners within 300 feet receive mailed notice. Contact Hayward's Planning Division or the City Council through hayward-ca.gov to comment or testify.

Sources & Official References

Other rules in Hayward

All Hayward rules

California rules heatmap·Compare Hayward to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Hayward, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Alameda County handle data center zoning & siting.

Fremont, CA
Light Restrictions
San Leandro, CA
Some Restrictions
Livermore, CA
Few Restrictions
Oakland, CA
Few Restrictions