Livermore, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Few Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Dedicated ordinance
None
Zones
I-2, I-3 industrial
By-right use
Manufacturing, R&D, office, warehousing
Discretionary review
Site Plan and Design Review
CEQA
Applies to review

Summary

Livermore has no data-center ordinance and no "data center" use category. Data centers locate in the I-2 (light industrial) and I-3 (heavy industrial) districts, permitted by right as manufacturing, research and development, warehousing, or office use, but each project requires Site Plan and Design Review approval.

The purpose of the I-2 (light industrial) district is to provide an environment exclusively for and conducive to the development of modern professional and administrative facilities, research institutions, and manufacturing operations, all of a non-nuisance type, and which are not proposed to be located in a campus- or park-like environment.

Source: Livermore Planning and Zoning Code (Industrial Districts) & Municipal Code Chapter 9.36 NoiseView official code

Full Breakdown

Livermore's Planning and Zoning Code (LPZC) does not name "data center" as a use. A data center is sited in the I-2 or I-3 industrial districts and classified into the nearest listed use - manufacturing, research and development, warehousing and distribution, or professional office - all permitted by right under LPZC 2-61-020. No conditional use permit is required for a standard facility, but Site Plan and Design Review approval is mandatory before construction under LPZC 2-61-080(A), and that review triggers CEQA. A facility relying on the catch-all "similar or compatible use" finding, or storing hazardous materials such as large diesel fuel for generators, needs a conditional use permit. Livermore has adopted no moratorium.

Violations & Fines

Building or operating a data center outside an I-2 or I-3 district, without required Site Plan and Design Review approval, or in breach of its performance standards, is a zoning violation enforced by Community Development through stop-work orders and abatement.

Frequently Asked Questions

Where can data centers be built in Livermore?
In the I-2 (light industrial) and I-3 (heavy industrial) districts. There is no data-center use category, so Planning classifies each project into the nearest listed industrial use under LPZC 2-61-020.
Does Livermore require a special permit for a data center?
A standard data center is permitted by right as an industrial use, but Site Plan and Design Review approval is required before construction, and that review triggers CEQA. A conditional use permit applies only in limited cases.
Has Livermore banned or paused data centers?
No. Livermore has adopted no moratorium and no data-center ordinance. Residents can advocate for tailored standards through the Planning Division and Planning Commission: livermoreca.gov/departments/community-development/planning

Sources & Official References

Other rules in Livermore

All Livermore rules

California rules heatmap·Compare Livermore to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Livermore, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Alameda County handle data center zoning & siting.

Fremont, CA
Light Restrictions
San Leandro, CA
Some Restrictions
Oakland, CA
Few Restrictions
Hayward, CA
Significant Restrictions