- ≤2 MW facility
- by-right in I-1 district
- >2 MW facility
- review required in I-4 district
- Review authority
- Section 18-113 process
- Utility clearance
- required at both tiers
- Added by
- Ordinance No. O-2026-7 (2-24-2026)
Summary
Lawton routes data center siting by size. A facility with peak electrical demand at or below 2 megawatts locates by right in the I-1 Restricted Manufacturing and Warehouse District. Anything larger has to clear a use-permitted-on-review hearing in the I-4 Heavy Industrial District under Section 18-6-17-682(A)(14), with the same electrical-provider clearance letter required either way.
A.The following uses may be permitted on review in accordance with the provisions of Section 18-113:...14.Digital asset mining business or data center, with a peak electrical demand greater than two (2) megawatts, subject to written clearance from the local electrical provider that there is sufficient infrastructure in place to safely support the use without negatively impacting service to existing customers; and15.Any use not otherwise authorized by this chapter.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 2 Update 1).
Full Breakdown
Section 18-6-17-682(A)(14) places 'digital asset mining business or data center, with a peak electrical demand greater than two (2) megawatts' on the I-4 Heavy Industrial District's uses-permitted-on-review list, meaning the operator must go through the Section 18-113 review process rather than obtaining a building permit outright. That review track sits alongside other high-impact I-4 uses on the same list, including acid manufacture, petroleum refining, and disposal plants, signaling that the city treats a large-scale mining or data center operation with the same siting caution as heavy industrial and waste uses.
The written electrical-provider clearance carries over unchanged from the smaller-scale I-1 rule in Section 18-6-14-646(A)(8): both thresholds require confirmation that sufficient infrastructure exists to safely support the use without negatively impacting service to existing customers, so the utility sign-off is not a substitute for the review process at the larger scale, it is an added condition on top of it. The I-4 district itself carries none of the enclosed-building or screening conditions attached to I-1's permitted-use list, but its general standards still apply, including screening walls 6 to 8 feet tall wherever the site abuts a residential district under Section 18-6-17-688. The city council added both the I-1 and I-4 digital-asset provisions in the same ordinance, No. O-2026-7, adopted February 24, 2026.
Violations & Fines
Locating a data center with peak demand above 2 megawatts in the I-4 district without first obtaining use-permitted-on-review approval under Section 18-113 violates Section 18-6-17-682(A)(14); building without that approval, or without the electrical provider's clearance letter, leaves the facility unauthorized regardless of the site's industrial zoning.
Frequently Asked Questions
Which zoning district allows a large data center in Lawton?
What review process applies to a data center in the I-4 district?
Does the electrical utility clearance requirement change based on the district?
Sources & Official References
Other rules in Lawton
Compare Lawton to another location·View the Oklahoma data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.