Key Facts

Commercial Corridor (CC)
Special Use Permit required
Light Industrial/Heavy Industrial
Permitted with additional standards
SUP size trigger
5,000 sq ft cumulative building area
Utility study
Required above 5,000 sq ft
Water requirement
Closed water loop system for SUP facilities
Governing sections
Appendix B §§ 5.1, 5.2.H.8.b

Summary

In the City of Wylie, a data center needs a Special Use Permit in the Commercial Corridor district and is permitted with additional standards in the Light Industrial and Heavy Industrial districts, per Appendix B's Land Use Chart. Any facility with 5,000 square feet or more of cumulative building area on a platted lot also needs its own Special Use Permit and a utility study under Section 5.2.H.8.

AG/30 SF-ED SF- 20/26 SF- 10/24 TH MF MH NS CR CC BG LI HI DTH SBO ... ... 8. Data Center S P* P* Per Approved SUP (L) ... b.Additional Provisions:(1)A Special Use Permit shall be required ... within the Commercial Corridor Zoning districts.(2)A Special Use Permit shall be required for facilities which have a cumulative building area at or over 5,000 square feet per platted lot.(3)Developments with a cumulative building area over 5,000 square feet shall provide a utility study demonstrating compatibility with existing city and franchisee infrastructure.(4)The following requirements shall be met for Data Centers with Special Use Permits:(a)Developments shall be required to provide a will service letter from the water provider.(b)Developments shall be on a closed water loop system.

Full Breakdown

Appendix B, Section 5.1's Land Use Chart lists Data Center with an S, meaning Special Use Permit required, in the Commercial Corridor (CC) district, and a P*, permitted by right subject to additional standards, in the Light Industrial (LI) and Heavy Industrial (HI) districts, with parking set Per Approved SUP rather than a fixed ratio. No other district on the chart, including any residential district or the Neighborhood Service, Community Retail or Business Government commercial districts, carries an entry for the use. Section 5.2.H.8.b layers on additional, size-triggered requirements that apply on top of the district-level table: a Special Use Permit is required within the Commercial Corridor district regardless of size, and separately, a Special Use Permit is required for any data center whose cumulative building area reaches or exceeds 5,000 square feet per platted lot, even in LI or HI where the base use is otherwise permitted by right.

Any development over that 5,000-square-foot threshold must also submit a utility study showing compatibility with existing city and franchise infrastructure. For a facility with an approved Special Use Permit, two further conditions apply: the developer must provide a will-service letter from the water provider, and the development must be built on a closed water loop system rather than drawing on the open municipal supply for cooling or process water. Together, the size trigger and the water conditions mean that even a by-right LI or HI site becomes an SUP-and-utility-study project once it crosses the 5,000-square-foot line.

Violations & Fines

Building or operating a data center in a district the Land Use Chart does not list, or exceeding the 5,000-square-foot cumulative building area threshold on a platted lot without first obtaining the Special Use Permit and utility study Section 5.2.H.8.b requires, is an unpermitted or noncompliant use subject to Code Enforcement action and denial of a certificate of occupancy. Operating without the required water-provider service letter or closed water loop system also breaches the SUP conditions and can trigger permit revocation.

Frequently Asked Questions

Which zoning districts allow a data center in Wylie?
The Commercial Corridor district by Special Use Permit, and the Light Industrial and Heavy Industrial districts by right subject to additional standards. Appendix B's Land Use Chart lists no entry for any residential or other commercial district.
Does a small data center need a Special Use Permit?
Only in the Commercial Corridor district, where an SUP is required regardless of size. In Light Industrial or Heavy Industrial, a Special Use Permit is triggered once the facility's cumulative building area reaches 5,000 square feet per platted lot, per Section 5.2.H.8.b.
What utility conditions apply to a large data center?
Once cumulative building area passes 5,000 square feet, the developer must submit a utility study on compatibility with city and franchise infrastructure, and any facility built under a Special Use Permit must provide a will-service letter from the water provider and operate on a closed water loop system.

Sources & Official References

Other rules in Wylie

All Wylie rules

Texas rules heatmap·Compare Wylie to another location·View the Texas data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Wylie, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.