Pasco, WA Environmental Rules: Boat Dock Permits (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Pier/ramp extension
At least 40 feet from OHWM
Pier/ramp width
Maximum 4 feet
Side setback
10 feet minimum
Float size cap
8 by 20 feet, 160 sq ft
Piling limit
Max 4 piles, 8-inch diameter
Work window
Nov 1 to Feb 28 only
Accessory launches
Prohibited for residential uses

Summary

Pasco regulates every dock, pier, or mooring buoy on the Columbia and Snake rivers under its Shoreline Master Program. A shoreline substantial development permit is required unless the project qualifies for a narrow exemption, and single-family docks must meet strict size, setback, and material limits.

(10) A dock or pier serving a single-family residence shall meet the following standards: (a) Piers and Ramps. (i) To prevent damage to shallow-water habitat, piers and ramps shall extend at least 40 feet perpendicular from the OHWM... (ii) Piers and ramps shall be no more than four feet in width... (12) Docks and piers shall be set back a minimum of 10 feet from side property lines, except that joint-use facilities may be located closer to, or upon, a side property line when agreed to by contract or covenant with the owners of the affected properties.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 4837, passed May 4, 2026).

Full Breakdown

100, a dock or pier serving a single-family residence must extend at least 40 feet perpendicular from the ordinary high water mark (OHWM), be no more than four feet wide, and sit at least two feet above the OHWM plane. Grating must cover 100 percent of the pier or float surface with at least 50 percent open area, and float components cannot exceed 8 by 20 feet or 160 square feet total. No electricity, boat lifts, paint, stain, or treated wood is allowed on the structure, and construction must occur only during the in-water work window of November 1 through February 28.

Piling is capped at eight inches in diameter, spaced at least 18 feet apart, with no more than four piles per project. Docks and piers must be set back at least 10 feet from side property lines unless neighbors record a joint-use agreement with the County Auditor. New subdivisions must record a plat restriction barring individual docks and instead designate a shared community moorage site. Boat launches accessory to single-family or multifamily residences are flatly prohibited; private launches are allowed only for water-dependent uses and marinas after showing public launches cannot serve the need. 080 must obtain a shoreline substantial development permit or shoreline special use permit before construction begins.

Violations & Fines

Building a dock, pier, or boat launch without the required shoreline substantial development permit, or in violation of the size, setback, material, or seasonal work-window standards in PMC 29.20.100, exposes the property owner to shoreline enforcement action by the City of Pasco Community & Economic Development Department, which can order removal or restoration of the site at the owner's expense and refer unresolved violations for civil penalties under the Shoreline Management Act.

Frequently Asked Questions

Do I need a permit to build a dock in Pasco?
Yes. Under PMC 29.15.010(d), any dock project not exempted under PMC 29.35.080 needs a shoreline substantial development permit or shoreline special use permit from the City before construction, in addition to meeting the design standards in PMC 29.20.100.
How far must a private dock extend into the water?
PMC 29.20.100(10)(a)(i) requires piers and ramps to extend at least 40 feet perpendicular from the ordinary high water mark to protect shallow-water habitat, though the City can grant case-by-case exceptions where 40 feet conflicts with navigation.
Can I install a boat lift on my dock?
No. PMC 29.20.100(10)(c)(ii) bars boat lifts or watercraft lifts of any type on or added to an overwater structure, with exceptions granted only case-by-case in coordination with other permitting agencies and within the 160-square-foot size limit.
Can a new subdivision along the river have individual docks?
No. PMC 29.20.100(13)(a) requires new subdivisions and short plats to record a restriction on the plat prohibiting individual docks and instead designate a shared or community moorage site owned in undivided interest by the property owners.

Sources & Official References

Other rules in Pasco

All Pasco rules

Compare Pasco to another location·View the Washington environmental rules overview

Get notified when Boat Dock Permits in Pasco, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.