Key Facts

Permit threshold
2,000 square feet or greater, cumulatively
Lawn exemption
Existing lawn on a single lot, not exceeding 10,000 square feet
Permit term
One year or until stabilized, whichever is shorter
Extension
Up to 12 months, if the Director finds it warranted
Major-project plan preparer
Oregon-licensed engineer, landscape architect, geologist or CPESC
Fees
Adopted by City Council resolution
Emergency contact
24-hour person and phone number on application

Summary

In the City of Albany, Oregon, an erosion prevention and sediment control (EPSC) permit is required for land-disturbing activities affecting an area of 2,000 square feet or greater, cumulatively. The Public Works Department does not issue it until the erosion controls are installed and the Director has inspected the site.

An erosion prevention and sediment control (EPSC) permit shall be obtained for land-disturbing activities affecting an area of 2,000 square feet or greater, cumulatively.

Full Breakdown

Chapter 12.40 of the Albany Municipal Code requires an EPSC permit under § 12.40.030 for land-disturbing activities affecting an area of 2,000 square feet or greater, cumulatively. Section 12.40.031 lists exemptions: activities affecting an area less than 2,000 square feet, cumulatively, replacement or re-establishment of an existing lawn on a single lot not exceeding 10,000 square feet, and agricultural activities. Exempt activities must still meet every requirement of Title 12 and are subject to Chapter 12.80.

The property owner applies to the City of Albany Public Works Department. Under § 12.40.032 the application identifies and describes the work, describes the land by legal description or street address, comes with an EPSC plan, identifies the person or entity doing the work, gives a 24-hour emergency contact person and phone number, is signed by the property owner, states financial responsibility for damages from noncompliance, and comes with fees adopted by City Council resolution under § 12.40.090. Section 12.40.040 requires the plan to meet the City of Albany Erosion Prevention and Sediment Control Manual. Major land-disturbing activities, as the manual defines them, need a plan prepared by a professional licensed in Oregon as a civil or environmental engineer, landscape architect or geologist, or a certified professional in erosion and sediment control (CPESC). Minor activities do not require a professional.

Digging cannot start early. Section 12.40.050 bars land-disturbing activities until the permit is issued, and the permit is not issued until the application and plan are submitted, the Director has given the plan initial approval, the erosion BMPs are installed under the plan, the Director has verified them in a site inspection, and the permit holder has made any changes the Director required after that inspection. Under § 12.40.034 a permit is valid for one year, or until the work is complete and surfaces are stabilized with permanent measures as verified by the Director, whichever is shorter, and up to a 12-month extension can be granted. Under § 12.40.033 a permit transfers only upon transfer of title. Eroded sediment leaving a site is also a prohibited discharge under § 12.10.010(1)(k).

Violations & Fines

Section 12.80.010 makes any violation of Title 12 unlawful, with each day a separate violation. Under § 12.80.035 the Director can order all related activities stopped until authorized to proceed, and under § 12.80.034 can suspend or revoke a permit issued on incorrect information or violated in its terms. Section 12.80.060 sets administrative fines of not less than $250.00 nor more than $2,500 per violation for endangering discharges, plus a misdemeanor with a fine of no less than $250.00 per violation. Enforcement notices can be appealed to the Director within 10 days.

Frequently Asked Questions

Do I need an EPSC permit to redo my lawn in Albany, Oregon?
Replacement or re-establishment of an existing lawn on a single lot can be exempted under § 12.40.031(1)(b) only when it does not exceed 10,000 square feet. Exempt work must still meet the requirements of Title 12 and is subject to Chapter 12.80. Other land-disturbing activities affecting 2,000 square feet or greater, cumulatively, need the permit.
Who has to prepare the erosion control plan?
Under § 12.40.040, major land-disturbing activities as defined in the City's EPSC manual require a plan prepared by a professional licensed in Oregon as a civil or environmental engineer, landscape architect or geologist, or a certified professional in erosion and sediment control. Minor land-disturbing activities do not require a professional to prepare the plan.
When can work begin after I apply?
Not until the permit is issued. Section 12.40.050 requires an approved plan, installed BMPs, a Director site inspection verifying the installation, and any additional BMPs the Director requires after that first inspection. Starting land-disturbing work before the permit issues is barred by the same section.
How long does an Albany EPSC permit last?
Under § 12.40.034, one year, or until land-disturbing activities are completed and surface conditions are stabilized with permanent measures as verified by the Director, whichever is shorter. Before expiration the permit holder can present a written request for an extension, and up to a 12-month extension can be granted, subject to the fees adopted under § 12.40.090.

Sources & Official References

Other rules in Albany

All Albany rules

Compare Albany to another location·View the Oregon environmental rules overview

Get notified when Erosion Control in Albany, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.