Arcadia, CA Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

One acre or more
Notice of Intent and SWPPP before a grading permit issues
Under one acre
Erosion and sediment control plan submitted before grading or building permit
Approval
Director's written approval before any construction activity begins
Plan preparer
Qualified SWPPP Developer for one acre or more
Structural BMPs
Designed by a licensed California Engineer
Penalty
Misdemeanor or infraction; each day a separate offense

Summary

In the City of Arcadia, California, Section 7827 requires every construction operator to submit evidence of required state permits and implement an erosion and sediment control plan before a grading or building permit issues. Sites of one acre or more need a Notice of Intent and a Stormwater Pollution Prevention Plan, and sites under one acre need a City-approved plan.

B.Best Management Practices for New Developments and Redevelopments. No grading permit shall be issued for any development with a disturbed area of one (1) acre or greater unless the applicant can show that (i) a Notice of Intent to comply with the State Construction Activity Stormwater Permit has been filed and (ii) a Stormwater Pollution Prevention Plan has been prepared. ... C.Erosion and Sediment Control Plan Required. In addition to any other requirements set forth in this Chapter, prior to obtaining a grading or building permit, each operator of any construction site of less than one (1) acre shall cause to be prepared and submitted to the City an erosion and sediment control plan. No operator of any construction activity shall commence any construction activity prior to receiving written approval of the erosion and sediment control plan from the Director. ... E.Erosion and Sediment Control Plan Development. Erosion and sediment control plans for construction sites of one acre or more must be developed and certified by a Qualified SWPPP Developer. Structural BMPs shall be designed by a licensed California Engineer.

Full Breakdown

Under Section 7827.A, before obtaining a grading or building permit, each operator of construction activity submits evidence to the Director that all applicable permits have been obtained, including the State Water Board's Construction Permit and State Water Board 401 Water Quality Certification. The operator implements the erosion and sediment control plan and BMPs the Director requires, and a SWPPP prepared under the General Construction Permit can substitute for the plan.

Section 7827.B blocks a grading permit for any development with a disturbed area of one (1) acre or greater unless a Notice of Intent to comply with the State Construction Activity Stormwater Permit has been filed and a Stormwater Pollution Prevention Plan has been prepared. Section 7827.C requires operators of sites under one (1) acre to prepare and submit an erosion and sediment control plan before a grading or building permit, and no construction activity starts before the Director gives written approval of the plan.

Plans for sites of less than one acre must address best management practices to control erosion and sediment and manage waste and non-stormwater in accordance with the Permit. Plans for sites of one acre or more cover all SWPPP elements plus methods to minimize the disturbed footprint and prevent soil compaction outside it, protection of native vegetation and trees, sediment and erosion control, controls to prevent tracking on and off the site, nonstormwater control such as vehicle washing and dewatering, material delivery and storage, spill prevention, waste management including concrete washout, the site Risk Level under the General Construction Permit, and the rationale for BMP selection including quantifying expected soil loss.

Section 7827.E requires plans for sites of one acre or more to be developed and certified by a Qualified SWPPP Developer and structural BMPs to be designed by a licensed California Engineer. Section 7827.F requires the landowner or landowner's agent to sign a certification acknowledging that failing to update the plan or to implement it can lead to revocation of grading and other permits and other sanctions.

Construction activity under Section 7810 covers any construction or demolition, clearing, grading, grubbing or excavation that results in land disturbance, and excludes emergency work to protect public health and safety and routine maintenance. Section 7810 defines a hillside as property where grading contemplates cut or fill on a natural slope of 25% or greater. Section 7830 lets Authorized Enforcement Officers enter to inspect, and Section 7830.E lets the City invoice reasonable inspection costs after an enforcement action.

Violations & Fines

Under Section 7831 a violation of the stormwater chapter is a misdemeanor, and the Authorized Enforcement Officer can charge it as an infraction. Each day is a separate offense under Section 7831.2. Officers can issue cease and desist orders (Section 7835), the City can seek injunctions and investigation costs by civil action (Section 7834), and the certification on the plan warns of revocation of grading and other permits. Appeals go to the Public Works Services Director within ten (10) days (Section 7838).

Frequently Asked Questions

Do I need an erosion control plan for a small project in Arcadia?
Yes, if the construction site is less than one (1) acre and you need a grading or building permit. Section 7827.C requires the operator to prepare and submit an erosion and sediment control plan, and no construction activity can start until the Director approves it in writing.
Who prepares the plan for a site of one acre or more?
Section 7827.E requires plans for construction sites of one acre or more to be developed and certified by a Qualified SWPPP Developer, and structural BMPs to be designed by a licensed California Engineer. Section 7827.B also requires a Notice of Intent under the State Construction Activity Stormwater Permit and a prepared SWPPP before any grading permit issues.
What must the plan cover on a large site?
Section 7827.D lists all SWPPP elements plus footprint minimization, protection of native vegetation and trees, sediment and erosion control, tracking controls, nonstormwater control, material management, spill prevention, waste management such as concrete washout, the site Risk Level, and the rationale for BMP selection including quantified expected soil loss.
What are the consequences of ignoring the plan?
The certification in Section 7827.F states that failing to update or properly implement the plan can result in revocation of grading and other permits and other sanctions provided by law. Section 7831 makes a violation a misdemeanor or infraction, and each day counts as a separate offense under Section 7831.2.

Sources & Official References

Other rules in Arcadia

All Arcadia rules

California rules heatmap·Compare Arcadia to another location·View the California environmental rules overview

Get notified when Erosion Control in Arcadia, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Los Angeles County handle erosion control.

Carson, CA
Some Restrictions
Compton, CA
Some Restrictions
Downey, CA
Significant Restrictions
El Monte, CA
Some Restrictions
Glendale, CA
Some Restrictions
Inglewood, CA
Some Restrictions
Lancaster, CA
Some Restrictions
Long Beach, CA
Some Restrictions