Bannock County, ID Environmental Rules: Erosion Control (2026)
Key Facts
- Trigger
- Average slope over 10 percent
- Required submission
- Topography, grading and erosion control plan
- 15-30% slopes
- Max 20 percent may be disturbed
- Over 30% slopes
- Max 5 percent may be disturbed
- Building ban
- No buildings on slopes 20%+
Summary
Before Bannock County will approve a conditional use permit on land with an average slope over 10 percent, the applicant must submit a grading plan showing existing and proposed topography along with specific erosion control measures. Planning and Development Services reviews the plan as part of the standard conditional use application.
6.For sites with an average slope greater than ten percent, a plan showing existing and proposed topography and grading and proposed erosion control measures,
Full Breakdown
Bannock County Code § 17.56.380(E) lists what a conditional use permit application must contain, and item (E)(6) specifically requires a grading plan with proposed erosion control measures whenever the site's average slope exceeds ten percent. That erosion-control submission works alongside the county's broader steep-slope limits in Section 17.52.530(B)(2): on slopes between 15 and 30 percent, no more than 20 percent of the area may be developed, regraded, or stripped of vegetation, and any disturbed soil must be reseeded to Natural Resource Conservation Service standards; on slopes over 30 percent that development ceiling drops to 5 percent of the area, and no buildings are permitted at all on slopes of 20 percent or greater.
Once a conditional use permit is granted, Section 17.56.420(A)(2) lets the Planning and Development Council attach ongoing conditions requiring installation and maintenance of erosion control measures for the life of the use, not just during construction. The planning director reviews the erosion control plan alongside the rest of the site plan, and county engineering staff can inspect drainage and grading work while it is under construction under Section 17.52.540(B), with authority to suspend a building permit if the site is not built to the approved plan.
Violations & Fines
Building or grading a sloped site without the required erosion control measures is enforced as a Title 17 violation under Bannock County Code § 17.56.030. The planning director is the enforcement officer; a first infraction is a flat $50 fine, a repeat infraction is $100, and a third violation after two prior convictions within 24 months becomes a misdemeanor punishable by up to $300 and six months in jail, with each day of noncompliance a separate offense. The county engineer can also compel correction of noncompliant grading or drainage work under Section 17.52.540(B), including suspending an active building permit.
Frequently Asked Questions
When does Bannock County require an erosion control plan?
How much of a steep slope can be disturbed in Bannock County?
Can I build on a steep slope in unincorporated Bannock County?
Who enforces erosion control requirements on a Bannock County construction site?
Sources & Official References
Other rules in Bannock County
Compare Bannock County to another location·View the Idaho environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.