Coconut Creek, FL Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit paperwork
SWPPP with every building, utilities and engineering permit application
First fine
$100 plus costs after notice and hearing
After 24 hours
Additional $250 fine
After 48 hours
$1,000, then $1,000 for each further day
Repeat violations
Up to $10,000 per day, plus stop-work
Conflicting rules
The most stringent requirement governs

Summary

Under Code § 13-257, every building, utilities and engineering permit application in the City of Coconut Creek needs a stormwater pollution prevention plan (SWPPP) that covers erosion and sediment control. A violation costs $100 plus costs, rising to $1,000 per day after 48 hours, and repeat violations can reach $10,000 per day with work stopped.

Adequate provisions shall be made for the management of stormwater, including erosion and sediment control, in accordance with the requirements of the city engineer, city's engineering standards, the Cocomar Water Control District (COCOMAR), the South Florida Water Management District (SFWMD), Florida Department of Environmental Protection (FDEP) and any other agency that may have jurisdiction over such activities. In case of any conflict, the most stringent requirements shall govern. ... (1)Stormwater pollution prevention plan. A stormwater pollution prevention plan (SWPPP) shall be developed and submitted with all applications for building, utilities and engineering permits. ... (3)Violations and penalties. Any person or entity found in violation of this section after notice and opportunity to be heard shall pay a fine of one hundred dollars ($100.00) plus costs.

Full Breakdown

Section 13-257 of the Land Development Code, titled Stormwater management, sets the erosion and sediment control standard for construction in the City of Coconut Creek. It requires adequate provisions for stormwater, including erosion and sediment control, in accordance with the city engineer, the city's engineering standards, the Cocomar Water Control District (COCOMAR), the South Florida Water Management District (SFWMD), the Florida Department of Environmental Protection (FDEP) and any other agency with jurisdiction. When those requirements conflict, the most stringent governs.

Subsection (1) requires a stormwater pollution prevention plan with every application for a building, utilities or engineering permit. The SWPPP must be in substantial compliance with Chapter 62.621, Florida Administrative Code. A copy of the SWPPP and the Notice of Intent (NOI) filed with FDEP counts as sufficient for city permitting. Subsection (2) sets the water quality rule: all runoff from a construction site flowing into a pipe or water body controlled by the city, COCOMAR or the State of Florida must be managed so it does not degrade the public drainage or conveyance system, and the city's standards track Sections 27-195 and 27-196 of the Broward County Code of Ordinances.

The section also puts spill costs on the builder. Contractors or owners are liable for the full cost of clean-up, fines or both when a harmful substance, including chemicals, oil, tar, asphalt, concrete, debris or soils, is spilled and can flow into a public conveyance system such as pipes, canals or lakes.

Stabilization after grading is covered in § 13-259(b). Graded roadway slopes and adjacent areas must be grassed at the earliest practical time and in all cases before the final paving course. Argentine Bahia grass seed is the minimum, and solid Argentine Bahia sod is called for where erosion or growing conditions are a problem. The contractor waters and mows the grass until the project is accepted, and the area needs a growing stand for at least one year after completion or acceptance.

Violations & Fines

Under § 13-257(3), a violation found after notice and opportunity to be heard costs $100 plus costs. Continuing beyond 24 hours after paying adds $250. Continuing beyond 48 hours brings $1,000, and every further day costs another $1,000. These fines stack on penalties from other agencies. Repeat violations can reach $10,000 per day, including a stop on the work when health, safety or the environment is at stake. Fine money goes to the stormwater management utility fund.

Frequently Asked Questions

Do I need a SWPPP to pull a building permit in Coconut Creek?
Yes. Section 13-257(1) requires a stormwater pollution prevention plan with all applications for building, utilities and engineering permits. It must substantially comply with Chapter 62.621, Florida Administrative Code. If you already filed a SWPPP and Notice of Intent with the Florida Department of Environmental Protection, a copy of both is considered sufficient for city permitting.
What are the fines for an erosion or runoff violation?
The first violation, after notice and a chance to be heard, costs $100 plus costs. If it continues beyond 24 hours after that payment, add $250. Beyond 48 hours the fine is $1,000, and $1,000 more for each day after. Repeat violations can reach $10,000 per day and the city can halt the work when the violation is serious.
Who pays if concrete or soil washes into a canal?
The contractor or the owner. Section 13-257 makes contractors or owners liable for the full cost of clean-up, fines or both when a harmful substance, listed to include chemicals, oil, tar, asphalt, concrete, debris and soils, is spilled and can flow into a public conveyance system, including pipes, canals or lakes.
Which agencies besides the city set erosion control standards?
Section 13-257 names the Cocomar Water Control District, the South Florida Water Management District and the Florida Department of Environmental Protection, plus any other agency with jurisdiction. When the requirements conflict, the most stringent governs. Construction runoff standards also follow Sections 27-195 and 27-196 of the Broward County Code of Ordinances.

Sources & Official References

Other rules in Coconut Creek

All Coconut Creek rules

Florida rules heatmap·Compare Coconut Creek to another location·View the Florida environmental rules overview

Get notified when Erosion Control in Coconut Creek, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Broward County handle erosion control.

Hollywood, FL
Some Restrictions
Pembroke Pines, FL
Some Restrictions
Pompano Beach, FL
Some Restrictions