Coeur d'Alene, ID Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Plan timing
Approved before any clearing, excavation or grading starts
Right of way cleaning
Curb to curb on a weekly basis
Final stabilization deadline
Within 21 days of removing temporary measures
Inspection notice
At least 48 hours before desired inspection time
Required inspections
After temporary controls installed and after final grading
Misdemeanor penalty
Up to $1,000 fine, 180 days jail, or both

Summary

In the City of Coeur d'Alene, an erosion, sediment and construction waste control plan must be approved before any site clearing, excavation or grading begins. It must include temporary and permanent measures built to city BMPs, and the permit holder and owner answer for upkeep. Violations are misdemeanors, and the city can stop work.

3. Erosion, Sediment And Construction Site Waste Control Standards: The design, testing, installation, and maintenance of erosion, sediment and construction site waste controls shall be in accordance with city approved best management practices (BMPs). An erosion, sediment and construction waste control plan shall be submitted and approved prior to initiation of any site clearing, excavation, and grading or other development activity. Both temporary and permanent erosion, sediment and construction waste control measures shall be included. The plan shall represent the minimum requirements for the site. Additional measures may be required by the city in the event of unexpected storm occurrences, repair or maintenance of existing systems, or replacement of nonfunctioning systems.

Full Breakdown

Erosion control in the City of Coeur d'Alene sits inside Chapter 13.30, the Stormwater Management Ordinance. Section 13.30.040(C)(3) requires the design, testing, installation and maintenance of erosion, sediment and construction site waste controls to follow city approved best management practices. The plan must be submitted and approved before any site clearing, excavation, grading or other development activity, and it must show both temporary and permanent measures. The plan is a minimum: the city can add measures after unexpected storms, for repair of existing systems, or to replace nonfunctioning ones. The permit holder and property owner maintain the measures unless the plan names another responsible party.

Section 13.30.050 sets the on-the-ground standards. Erosion, sediment or pollutants from construction that reach public property, or private property the permit holder does not control, must be eliminated to the maximum extent practicable. Site owners and permit holders must minimize tracking of mud, dirt, sand, gravel, rock or debris onto the public right of way and pay for cleanup or reimburse the city, and public rights of way must be cleaned curb to curb on a weekly basis. Construction ramps must use material that will not erode and cannot block stormwater runoff. Debris, dirt, aggregate, excavated material and supplies stay off the public right of way unless the city permits them in writing.

A lot cannot sit vacant after the topsoil is disturbed or natural cover removed unless control measures keep material from migrating off site. Sediment from disturbed soils must be detained on site and either stabilized there or removed in an approved manner, and channels that concentrate stormwater need protection and energy dissipation. Temporary controls come out only after final site stabilization, and the trapped sediment and disturbed soil must be permanently stabilized within 21 days of removal.

Under § 13.30.080, sites must pass a city inspection after the temporary controls are installed and again after final grading or permanent drainage and erosion facilities are complete. The permit holder schedules these through the city building department at least 48 hours ahead, and no work proceeds until the inspection is approved.

Violations & Fines

Under § 13.30.120, violating Chapter 13.30 is a misdemeanor punished under title 1, chapter 1.28, and each day is a separate offense. Section 1.28.010 sets a fine of up to $1,000, up to 180 days in jail, or both. Under § 13.30.070 the city can stop work and withhold further building permits, and § 13.30.120 allows denial or suspension of permits and certificates of occupancy.

Frequently Asked Questions

When must the erosion control plan be approved in Coeur d'Alene?
Before any work starts. Section 13.30.040 requires the erosion, sediment and construction waste control plan to be submitted and approved prior to any site clearing, excavation, grading or other development activity, and it must cover both temporary and permanent measures. Section 13.30.050 adds that no construction can take place without a valid stormwater management plan.
Who cleans mud tracked onto city streets from a construction site?
The site owner or permit holder. Section 13.30.050 makes them responsible for cleanup of the public right of way or private property they do not control, or for reimbursing the city's expenses. At a minimum, public rights of way must be cleaned curb to curb on a weekly basis.
Can I leave a cleared lot bare in Coeur d'Alene?
Not without controls. Section 13.30.050 bars any owner or lessee from leaving property unoccupied, unused, vacant or undeveloped after the topsoil is disturbed or natural cover removed, unless measures prevent mud, sand, dirt, gravel or other material from migrating off site and entering the public right of way or a stormwater system.
How do I schedule the required erosion control inspections?
The permit holder schedules them through the city building department under § 13.30.080. Inspections must be requested at least 48 hours before the desired time. A passed inspection is required after temporary controls are installed and after final grading or permanent drainage and erosion facilities are complete.

Sources & Official References

Other rules in Coeur d'Alene

All Coeur d'Alene rules

Compare Coeur d'Alene to another location·View the Idaho environmental rules overview

Get notified when Erosion Control in Coeur d'Alene, ID changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.