Edmond, OK Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

BMP responsibility
Developer/Owner, for project duration
State permit required
ODEQ General Permit OKR10
State permit trigger
1+ acre disturbed area
Re-inspection fee
$500 per occurrence
Enforcement
City Engineer / Stop Work Order

Summary

Developers and owners building in Edmond must design, install, and maintain erosion and sediment control BMPs before grading starts, and must hold both a City permit and the state's ODEQ OKR10 stormwater discharge permit.

The Developer/Owner shall remain responsible for the design, installation, inspection, and continual maintenance of all erosion and sediment control Best Management Practices (BMPs). The Developer/Owner shall obtain the necessary permits from the Oklahoma Department of Environmental Quality (ODEQ) and the City of Edmond prior to any construction activities. Installation of erosion and sediment control BMPs is considered the number one priority before construction activity takes place. Appropriate and acceptable BMPs are outlined in the City of Edmond Standard Drainage Policy STD-400. The ODEQ's "General Permit OKR10 For Storm Water Discharges From Construction Activities Within The State Of Oklahoma" is hereby adopted by reference and its requirements shall apply to all sites covered by that permit. A copy is available for public inspection in the office of the City Engineer. (Ord. 2382, November 1997; Ord. 2853, § 1, May 24, 2004; Ord. 3053, § 3, November 13, 2006).

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 39).

Full Breakdown

Edmond treats erosion and sediment control as the first priority on any construction site: Best Management Practices must be installed before land-disturbing work begins, and the Developer/Owner stays responsible for their design, inspection, and upkeep for the project's duration. Sites disturbing one acre or more must also file the ODEQ Notice of Intent and hold the state's General Permit OKR10 before work starts. If the City Engineer finds BMPs failing on inspection, a Stop Work Order and Notice of Violation follow, and work stays halted until the site is brought back into compliance.

Violations & Fines

A failing or missing BMP triggers a Stop Work Order; work cannot resume until compliance is restored, a $500 re-inspection fee is paid, and a City-set cash deposit is posted under § 23.20.050(d).

Frequently Asked Questions

Do I need a permit to control erosion on a construction site in Edmond?
BMPs must go in before construction starts, and sites disturbing an acre or more also need the ODEQ OKR10 state permit.
What happens if erosion controls fail inspection?
The City Engineer can issue a Stop Work Order; work stays halted until BMPs are fixed, a $500 re-inspection fee is paid, and a cash deposit is posted.

Sources & Official References

Other rules in Edmond

All Edmond rules

Compare Edmond to another location·View the Oklahoma environmental rules overview

Get notified when Erosion Control in Edmond, OK changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in this county handle erosion control.

Midwest City, OK
Some Restrictions
Oklahoma City, OK
Some Restrictions