Skip to main content
CityRuleLookup

San Diego County, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
County Code § 67.809
Required BMPs
erosion, sediment, run-on/run-off control
Plan due
before construction permit issues
Enforced by
Director of Public Works
Max penalty
$1,000 fine or 6 months jail

Summary

Construction projects with land disturbance in unincorporated San Diego County must install and maintain erosion control, sediment control, and run-on/run-off control BMPs year-round, with a stormwater quality plan submitted before permit issuance.

City-specific rules exist: Vista, San Marcos, Escondido, El Cajon, Chula Vista, San Diego, Carlsbad, and Oceanside have their own erosion control rules that differ from San Diego County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

All owners of land on which a construction project is performed and all persons performing the work...shall ensure that the following additional types of BMPs shall be installed, implemented, and maintained year round: (1) Project planning; (2) Good site management "Housekeeping", including waste management; (3) Non-stormwater management; (4) Erosion control; (5) Sediment control; (6) Run-on and run-off control; and (7) Active/passive sediment treatment systems, where applicable.

Source: County Grading Ordinance Div. 7View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-141: Administrative: Current through Ord. No. 11007 (N.S.), effective 7-10-26 | Regulatory: Current through Ord. No. 11008 (N.S.), effective 7-24-26).

Full Breakdown

Under the county's Watershed Protection, Stormwater Management and Discharge Control Ordinance (County Code Chapter 67, Division 7, Title 6), every owner and contractor on a construction project involving land disturbance in unincorporated San Diego County must install erosion control, sediment control, and run-on/run-off control BMPs, inspecting and maintaining them after every rain event. Before a permit issues, the applicant must submit a stormwater quality management plan or erosion/pollution control plan to the Director of Public Works or the authorized enforcement official. The rule applies whether or not a permit is otherwise required for the work.

Violations & Fines

First-time infractions draw up to a $100 fine, rising to $200 and then $500 for repeat violations within a year; a misdemeanor charge carries up to 6 months in jail or a $1,000 fine, with each day of noncompliance a separate offense.

Frequently Asked Questions

Does this rule apply inside the City of San Diego?
No. It governs only unincorporated San Diego County; the City of San Diego and the county's 17 other incorporated cities enforce their own stormwater ordinances.
Is a building permit required to trigger the BMP requirement?
No. Section 67.809(a) applies to any construction project with land disturbance activities in the county, regardless of whether a permit is required for the work.

Sources & Official References

Other rules in San Diego County

All San Diego County rules

California rules heatmap·Compare San Diego County to another location·View the California environmental rules overview

Get notified when Erosion Control in San Diego County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.